Question 21 Choose 1
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?
Show answerHide answer

Correct answer: C Schedule regular project audits.

Question 22 Choose 2
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)
Show answerHide answer

Correct answer: C, E Analyze the business benefits criteria and assumptionsSchedule a project review meeting to analyze the root cause

Question 23 Choose 1
A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?
Show answerHide answer

Correct answer: B Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

Question 24 Choose 1
A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?
Show answerHide answer

Correct answer: D Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Question 25 Choose 1
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?
Show answerHide answer

Correct answer: D Request that the project team develop a release plan and roadmap for the project.

Question 26 Choose 1
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?
Show answerHide answer

Correct answer: D Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Question 27 Choose 1
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: D Set expectations for contributions ahead of the meeting

Question 28 Choose 1
A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?
Show answerHide answer

Correct answer: D Assess the influence and power of the employee to see if the employee will add value.

Question 29 Choose 1
Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to ensure the project is delivered successfully?
Show answerHide answer

Correct answer: B Invite the vendor to a meeting to discuss the concerns.

Question 30 Choose 1
A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?
Show answerHide answer

Correct answer: A Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt