Question 11 Choose 1
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?
Show answerHide answer

Correct answer: C Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

Question 12 Choose 1
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?
Show answerHide answer

Correct answer: B Share the existing technical architect so they can be allocated to the current project and other projects.

Question 13 Choose 1
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?
Show answerHide answer

Correct answer: B Create a risk register to identify, capture, review, and manage risks using a risk management process.

Question 14 Choose 2
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)
Show answerHide answer

Correct answer: B, D Analyze the impact of the issue and submit a change request to update the project schedule.Extend the project deadline and update the project schedule to reflect the delay.

Question 15 Choose 1
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
Show answerHide answer

Correct answer: A Meet with the project team to develop a proper resolution to the issue.

Question 16 Choose 1
A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?
Show answerHide answer

Correct answer: D Use a formal approach using procurement policies, procedures, forms, and work instructions.

Question 17 Choose 1
A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?
Show answerHide answer

Correct answer: D Understand the scope complexity and project magnitude prior to determining which approach to use.

Question 18 Choose 1
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?
Show answerHide answer

Correct answer: B Risk occurred

Question 19 Choose 1
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development.

Which action should the project manager take to resolve the quality issues?
Show answerHide answer

Correct answer: A Plan for continuous validation of the product.

Question 20 Choose 1
A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?
Show answerHide answer

Correct answer: C Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank