A prefeasibility study for a new renewable energy project is nearing approval. To ensure
that the project time lines are maintained, activities associated with the feasibility study
must continue while the prefeasibility study is being approved.
How should the project manager proceed?
Show answerHide answer
Correct answer: CObtain approval to proceed with the feasibility study as a parallel activity while the
prefeasibility study is approved
Question 12Choose 1
A project manager is managing a new development program to automate some technical
functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount
of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is
already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to
ensure project success?
Show answerHide answer
Correct answer: BShare the existing technical architect so they can be allocated to the current project and
other projects.
Question 13Choose 1
An organization is transitioning to agile. The project manager is discussing how to manage
risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low.
What should the project manager do?
Show answerHide answer
Correct answer: BCreate a risk register to identify, capture, review, and manage risks using a risk
management process.
Question 14Choose 2
A project team member raised a risk that the threat of country-wide power cuts may affect
the project time line for a software development project. In the last month, this risk
materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two)
Show answerHide answer
Correct answer: B, DAnalyze the impact of the issue and submit a change request to update the project
schedule.Extend the project deadline and update the project schedule to reflect the delay.
Question 15Choose 1
An iteration is almost finished, but the team is struggling to complete the stories that require
more time. What should the project manager do first?
Show answerHide answer
Correct answer: AMeet with the project team to develop a proper resolution to the issue.
Question 16Choose 1
A project manager is leading a project that will be delivered using a Scrum framework. The
organization has an innovative project management office (PMO) that fully supports agile
and also has a very friendly procurement team. A new vendor needs to be engaged to
provide more developers for a new reporting platform.
What should the project manager do?
Show answerHide answer
Correct answer: DUse a formal approach using procurement policies, procedures, forms, and work
instructions.
Question 17Choose 1
A project manager who is experienced in predictive and adaptive approaches has been
assigned to a new project. Most of the project
stakeholders have only worked on predictive projects, and only a few have been exposed
to adaptive projects.
What should the project manager do?
Show answerHide answer
Correct answer: DUnderstand the scope complexity and project magnitude prior to determining which
approach to use.
Question 18Choose 1
A project manager is working on a software development project. The project manager and
the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the
risk management plan to determine how to manage the risk. Once the risk management
strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
Show answerHide answer
Correct answer: BRisk occurred
Question 19Choose 1
A project manager is working on a product development project. When the product is
delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
Show answerHide answer
Correct answer: APlan for continuous validation of the product.
Question 20Choose 1
A project manager has taken over a project that has been without a project manager for the
last couple of weeks. The team is feeling lost and there are a few team
members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?
Show answerHide answer
Correct answer: CSet short-term goals in order to create a winning culture internally and praise team
members for achieving them.