A project manager is leading a project that has been in execution for 1 year. An
experienced team member is performing well, but often disagrees with the project manager
and refuses to implement their decisions. Part of the team supports the team member's
defiance, while the other team members do not.
What should the project manager do?
Show answerHide answer
Correct answer: CUnderstand what the team member wants and find possible opportunities to address it.
Question 32Choose 1
A project manager is leading a cross-organizational project that is replacing a platform on
which various solutions used by 15 business units were built. The project is part of a large
program of work, and some of the resources are shared with other projects outside of the
program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage
interdependencies?
Show answerHide answer
Correct answer: DProgram managers
Question 33Choose 1
A product owner is invited to a sprint review meeting. At the end of the review, the product
owner says that the increment is ready to be delivered to the customer.
What conclusion should the project manager come to with regard to the product owner's
statement?
Show answerHide answer
Correct answer: CThe product owner has evaluated the product against the definition of done (DoD).
Question 34Choose 1
A company wants to be a pioneer in its industry and has announced the launch date of a
new innovative product. After the first sprint planning, the
team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?
Show answerHide answer
Correct answer: CAssist the team in defining a minimum viable product (MVP) by the launch date.
Question 35Choose 1
A team is using an agile approach to maintain the project backlog. A new project obstacle
was identified as a blocker and added to the backlog list. The team is facing challenges to
remove this obstacle
What should the project manager do next?
Show answerHide answer
Correct answer: DMake changes to reprioritize the backlog because of the obstacle.
Question 36Choose 1
Due to unforeseen circumstances, a contractor was unable to mobilize the project team,
which was necessary to conduct face-to-face meetings and discussions. Virtual meetings
were subsequently put in place, but the local project team and end users now face a
communication gap that is causing the team's low performance.
What should the project manager do?
Show answerHide answer
Correct answer: DReassess continually to remove blockers for the team.
Question 37Choose 1
A company has decided to initiate a project to eliminate a sales channel that has been
unprofitable for the past 3 years. Some members of the project team are pessimistic about
the project.
What should the project manager do in this situation?
Show answerHide answer
Correct answer: CCommunicate the project's impact and plans to engage the project team throughout the
project.
Question 38
A project manager has been assigned to a software development project that will undergo
several iterations until the customer is satisfied. Match the tool or technique on the left that
the project manager should utilize to ensure tasks are efficiently managed to the correct
task on the right.
Show answerHide answer
Explanation
Question 39Choose 1
A project team is working on a product that is planned for multiple iterations. They are
delivering incremental value.
When should the value be demonstrated?
Show answerHide answer
Correct answer: CAt the end of each and every iteration
Question 40Choose 1
A new marketing vice president just joined a software startup and is concerned that the
agile model does not provide the needed accountability for their role. What should the
responsible project manager do to ensure the vice president is comfortable with the project
meeting its agreements?
Show answerHide answer
Correct answer: BFoster an environment of open communication where all parties can discuss issues and
agree on objectives.