PMI certification · Exam PMP

PMP Mock Exam Page 4

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 5: Exam Pool E, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 5: Exam Pool E questions

31–40 of 80 free
Question 31 Choose 1
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?
Show answerHide answer

Correct answer: C Understand what the team member wants and find possible opportunities to address it.

Question 32 Choose 1
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?
Show answerHide answer

Correct answer: D Program managers

Question 33 Choose 1
A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?
Show answerHide answer

Correct answer: C The product owner has evaluated the product against the definition of done (DoD).

Question 34 Choose 1
A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?
Show answerHide answer

Correct answer: C Assist the team in defining a minimum viable product (MVP) by the launch date.

Question 35 Choose 1
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?
Show answerHide answer

Correct answer: D Make changes to reprioritize the backlog because of the obstacle.

Question 36 Choose 1
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?
Show answerHide answer

Correct answer: D Reassess continually to remove blockers for the team.

Question 37 Choose 1
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?
Show answerHide answer

Correct answer: C Communicate the project's impact and plans to engage the project team throughout the project.

Question 38
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
Show answerHide answer

Explanation

Question 39 Choose 1
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?
Show answerHide answer

Correct answer: C At the end of each and every iteration

Question 40 Choose 1
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
Show answerHide answer

Correct answer: B Foster an environment of open communication where all parties can discuss issues and agree on objectives.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt