Question 41 Choose 1
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?
Show answerHide answer

Correct answer: C Make documentation a standard part of the definition of done (DoD).

Question 42 Choose 1
A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became concerned that the product quality will be sacrificed.

What should the project manager do?
Show answerHide answer

Correct answer: C Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

Question 43 Choose 1
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?
Show answerHide answer

Correct answer: B Used bottom-up estimating

Question 44 Choose 1
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
Show answerHide answer

Correct answer: C Promote, inspire, and follow the stakeholder engagement process.

Question 45 Choose 1
A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?
Show answerHide answer

Correct answer: D Include compliance within the development tools.

Question 46 Choose 1
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
Show answerHide answer

Correct answer: B Coach the project owner about the implications of unplanned meetings.

Question 47 Choose 1
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
Show answerHide answer

Correct answer: C Analyze the stakeholders.

Question 48 Choose 1
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?
Show answerHide answer

Correct answer: A Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.

Question 49 Choose 1
In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?
Show answerHide answer

Correct answer: C Start the organization's change control process via a change request.

Question 50 Choose 1
During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
Show answerHide answer

Correct answer: C Review the backlog and find opportunities to reprioritize the work and reduce the project scope

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt