A project team is performing extremely well when it comes to delivering the value-added
features to the customer in each sprint. However, they are missing the
documentation portion and the project manager must find a way to make sure the
documentation is kept current.
Which action should the project manager take?
Show answerHide answer
Correct answer: CMake documentation a standard part of the definition of done (DoD).
Question 42Choose 1
A project manager's customer is new to agile approaches. When the customer found out
that the project was going to use an agile approach, the customer became
concerned that the product quality will be sacrificed.
What should the project manager do?
Show answerHide answer
Correct answer: CEnsure the team demonstrates product features to this customer regularly to collect
feedback and improve as needed.
Question 43Choose 1
A project manager who takes over halfway through a project determines that the cost
performance index (CPI) is 0.65. A detailed audit identifies that the project cost was
analogously estimated, and the audit team thinks that something was missing in the way
the estimates were done.
What should have been done to avoid this problem?
Show answerHide answer
Correct answer: BUsed bottom-up estimating
Question 44Choose 1
In a highly politicized organizational environment, the stakeholders are driven by their own
operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
Show answerHide answer
Correct answer: CPromote, inspire, and follow the stakeholder engagement process.
Question 45Choose 1
A project team needs to follow regulatory compliance guidelines that are mandatory for the
project. What should the project manager do to ensure compliance adherence?
Show answerHide answer
Correct answer: DInclude compliance within the development tools.
Question 46Choose 1
In an agile project, the project owner has repeatedly called for ad hoc meetings with team
members. What should the project manager do?
Show answerHide answer
Correct answer: BCoach the project owner about the implications of unplanned meetings.
Question 47Choose 1
A project manager just finished a meeting to identify the main stakeholders of the project.
What should the project manager do next?
Show answerHide answer
Correct answer: CAnalyze the stakeholders.
Question 48Choose 1
A project manager is assigned to a project that is in the execution phase that has different
types of stakeholders. Some of the stakeholders are very interested in the project, whereas
other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
Show answerHide answer
Correct answer: ALook at the stakeholder assessment matrix to find stakeholders' interests and make
updates if necessary.
Question 49Choose 1
In a marine construction project, the project manager is informed by the marine authority
that the work permit will not be issued until certain environmental reinforcement work has
been completed. After reviewing the project management plan, the reinforcement work is
not included in the project scope.
What should the project manager do?
Show answerHide answer
Correct answer: CStart the organization's change control process via a change request.
Question 50Choose 1
During execution of an agile project, a project manager realizes the budget is almost
completely used, but the project is not close to being completed. What should the project
manager do to address this concern?
Show answerHide answer
Correct answer: CReview the backlog and find opportunities to reprioritize the work and reduce the project