Question 51 Choose 1
A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?
Show answerHide answer

Correct answer: C Consult the communications management plan.

Question 52 Choose 1
An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?
Show answerHide answer

Correct answer: B Ask the PMO to review the framework

Question 53 Choose 1
A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?
Show answerHide answer

Correct answer: A Ensure the change management plan highlights this requirement to prevent future issues.

Question 54 Choose 1
A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?
Show answerHide answer

Correct answer: A Review the risks throughout project execution.

Question 55 Choose 1
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?
Show answerHide answer

Correct answer: B Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

Question 56 Choose 1
A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?
Show answerHide answer

Correct answer: C Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand

Question 57 Choose 1
A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?
Show answerHide answer

Correct answer: B Recommend the team member for effective communication training and support their career development interests.

Question 58 Choose 1
A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?
Show answerHide answer

Correct answer: B Propose an approach based on value measurement, such as the use of objectives and key results.

Question 59 Choose 1
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?
Show answerHide answer

Correct answer: C Hold a brainstorming session to identify the root cause of the complaints.

Question 60 Choose 2
A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)
Show answerHide answer

Correct answer: A, E Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.Engage all stakeholders in the project including the unsupportive stakeholders.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt