A project manager is assigned to a project team midway through execution. Several
dependencies are impacting the project, and the project manager feels the team is not
adequately informed of the impacting changes.
What should the project manager do first?
Show answerHide answer
Correct answer: CConsult the communications management plan.
Question 52Choose 1
An organization initiated a project in a complex program. The project lead notices that the
team is demotivated because the current project framework implemented by the project
management office (PMO) is not compatible with agile delivery
What should the project lead do?
Show answerHide answer
Correct answer: BAsk the PMO to review the framework
Question 53Choose 1
A project manager is reviewing the lessons learned for an historical project. The review
identifies that the client's engineer was adamant that they review all changes, even those
not identified in the contract.
How should the project manager deal with this when planning the project?
Show answerHide answer
Correct answer: AEnsure the change management plan highlights this requirement to prevent future
issues.
Question 54Choose 1
A project manager for a technologically complex engagement reviews the key project
indicators with the main stakeholders on a regular basis. During one of the meetings,
the project sponsor explains that they are using the project manager's risk register as a
way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk
register?
Show answerHide answer
Correct answer: AReview the risks throughout project execution.
Question 55Choose 1
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific
resources to all of the project tasks.
What should the project manager do?
Show answerHide answer
Correct answer: BAssign the unallocated tasks to the functional role and then reallocate when the
resources are available.
Question 56Choose 1
A CEO of a general contracting company urgently asks the project manager to sign up two
project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above
their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
Show answerHide answer
Correct answer: CObserved and assessed the competencies and skills of the team members and
analyzed the training material beforehand
Question 57Choose 1
A team member has very strong technical skills and is interested in a leadership role. A
leadership position opens up outside of the team in the organization. The project manager
has observed that the team member has a major gap in communicating in a professional
manner.
What should the project manager do?
Show answerHide answer
Correct answer: BRecommend the team member for effective communication training and support their
career development interests.
Question 58Choose 1
A company is undergoing a digital transformation and is changing its project portfolio to an
agile approach. As a result, the leadership is looking to update the performance measuring
system for the workforce.
What should the project manager propose?
Show answerHide answer
Correct answer: BPropose an approach based on value measurement, such as the use of objectives and
key results.
Question 59Choose 1
During a team meeting, the new agile project manager becomes aware that there are many
complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees
who confirmed that the project was stable.
How should the new project manager address these concerns?
Show answerHide answer
Correct answer: CHold a brainstorming session to identify the root cause of the complaints.
Question 60Choose 2
A project manager is managing an internal project with a tight budget and schedule. While
executing the project, the project manager realizes that
some stakeholders are working against the success targets of the project.
What should the project manager do to ensure successful project delivery? (Choose two)
Show answerHide answer
Correct answer: A, EUpdate the project stakeholder analysis and methods to satisfy the stakeholders’
requirements.Engage all stakeholders in the project including the unsupportive stakeholders.