A project manager implementing a hybrid project is dealing with multiple stakeholders in a
rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
Show answerHide answer
Correct answer: DUse iterative life cycles involving stakeholders to enable the team to improve the product
end result through successive prototypes.
Question 62Choose 1
A project manager was recently assigned to a project that is in the execution phase and is
experiencing roadblocks. During a review of the
processes and procedures, the project manager notices similarities to a previous project
that experienced similar roadblocks. The project manager
reviews the task schedule and finds that certain tasks are well behind expectations. In
speaking with the project team, the project manager
confirms that the team is following the processes exactly.
What should the project manager do?
Show answerHide answer
Correct answer: CReview and amend the processes to ensure only value-adding activities are present.
Question 63Choose 1
A project manager is assigned to an organizational transformation project. The company
typically defines individual performance plans at the beginning of the year, and functional
managers conduct feedback reviews at the end of the year. The transformation project
team members are concerned that the work they are doing for this project is not aligned
with the work included in their individual performance plan for the year.
What should the project manager do?
Show answerHide answer
Correct answer: AMeet with the functional managers to align the expected frequency and results reporting
for the team members.
Question 64Choose 1
A project manage is in the middle of an angle project comprised of 100 user stories broken
down into five iterations. Each user story is worth U$$50. The actual expenditure is
U$$2,00 and 50 user stories have been delivered.
Which statement is true?
Show answerHide answer
Correct answer: BThe project is under budget and on schedule.
Question 65Choose 1
A project team was hired to perform on-site duties, but there were unexpected
circumstances that required the entire team to work remotely Some team members
returned to their hometowns and they are now requesting reimbursement for operational
expenditures
What should the project manager do?
Show answerHide answer
Correct answer: AFollow the Perform integrated Change Control process and submit a change request
Question 66Choose 1
During the last two iterations of a project, one of the team members had low performance.
The project manager conducted two feedback sessions with the team member and
escalated the issue to the resource manager and project sponsor, but there has been no
improvement.
What should the project manager do next?
Show answerHide answer
Correct answer: CRequest a new resource to execute the activities.
Question 67Choose 1
A company is running a project to eliminate a sales channel that has been unprofitable for
the past 3 years. A key stakeholder from another area, who has legacy ties to that sales
channel, objects to the project.
What should the project manager do in this situation?
Show answerHide answer
Correct answer: AAssess the impact of the stakeholder and engage properly.
Question 68Choose 1
A project manager is newly assigned to the second phase of an ongoing project. During the
implementation, a defect occurred and no one knows how to fix it, as the former
engineering team has moved to another project. The customer warns that previously, this
defect negatively affected the project schedule.
What should the project manager do first?
Show answerHide answer
Correct answer: CCheck the organizational process assets (OPAs).
Question 69Choose 1
A project manager has been managing an agile project for 6 months. Over the last two
iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the
expected velocity?
Show answerHide answer
Correct answer: AUse retrospectives to better understand the new technology's impact on the schedule,
map the skill gaps, and adjust the team accordingly.
Question 70Choose 1
A project manager is in the middle of handling a major upgrade to an existing product. The
project manager learns that the resources initially promised as part of the project are being
moved to another priority project.
What should the project manager do?
Show answerHide answer
Correct answer: DPerform an impact analysis to see the effect on the project.