Question 61 Choose 1
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?
Show answerHide answer

Correct answer: C 1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

Question 62 Choose 1
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?
Show answerHide answer

Correct answer: C Paired work and the customer role method.

Question 63 Choose 1
A company that is heavily focused on delivering projects using predictive approaches on- boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?
Show answerHide answer

Correct answer: D Break down the requirements and prioritize the requirements into iterative work packages

Question 64 Choose 1
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?
Show answerHide answer

Correct answer: D Meet with the project team to understand the issue and define actions.

Question 65 Choose 3
A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
Show answerHide answer

Correct answer: B, D, E Create a change request with the scope of the new internal projects.Create a work breakdown structure (WBS) of the new scope with the internal projectsManage the quality of the delivery

Question 66 Choose 1
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
Show answerHide answer

Correct answer: D Validated each stakeholder's understanding during the kick-off meeting

Question 67 Choose 1
A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?
Show answerHide answer

Correct answer: A Request that the customer reviews and clarifies feature definitions for the current sprint

Question 68 Choose 1
An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?
Show answerHide answer

Correct answer: B Get commitment from the team to include all of the required regulations

Question 69 Choose 1
The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.

What should the project manager do?
Show answerHide answer

Correct answer: C Determine cross-dependencies and plan a spike in the next spont

Question 70 Choose 1
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?
Show answerHide answer

Correct answer: B Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt