A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?
Show answerHide answer

Correct answer: C Continually survey the quality of the deliverable

Question 52 Choose 2
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
Show answerHide answer

Correct answer: A, B Ask the stakeholders about the priority of this changeAsk the product owner to review the product backlog

Question 53 Choose 1
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
Show answerHide answer

Correct answer: C Schedule a meeting with the product owner and finance team to agree on course corrections

Question 54 Choose 1
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued
Show answerHide answer

Correct answer: A Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

Question 55 Choose 1
During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?
Show answerHide answer

Correct answer: D Review the risk management plan to evaluate the probability and impact of these delays

Question 56 Choose 1
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
Show answerHide answer

Correct answer: D Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

Question 57 Choose 1
A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?
Show answerHide answer

Correct answer: B Meet with the project team to analyze the actual cost to determine deviations

Question 58 Choose 1
The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?
Show answerHide answer

Correct answer: D Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Question 59 Choose 2
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two)
Show answerHide answer

Correct answer: A, C Revisit the team's discussion on team behaviors and normsCoach the new team member to improve engagement with the team.

Question 60 Choose 1
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?
Show answerHide answer

Correct answer: D Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt