A team averages 100 story points per iteration. The team estimates there are about
another 2,000 points remaining and about 20 iterations remaining. One of the team
members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
Show answerHide answer
Correct answer: BReview this method with the team.
Question 272Choose 1
A project manager is working on a construction project. The company owner asks the
project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
Show answerHide answer
Correct answer: BContact a subject matter expert (SME) for advice and consultation.
Question 273Choose 1
A predictive project team come across a scenario where they need to use some agile tools
and methods. However, they did not feel this was appropriate since their organizational
project management processes did not mention this.
What should the project manager do in this scenario?
Show answerHide answer
Correct answer: CWork with the team to determine appropriate project methods and practices and
implement them.
Question 274Choose 1
A project manager has been assigned to a project where collaboration with the business is
a critical key factor. The project manager is not sure about which approach to use. A senior
project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Show answerHide answer
Correct answer: BSuggest using an agile approach since customer and team collaboration is critical for
project success.
Question 275Choose 1
In a standup meeting a team member has been providing the same update for five
consecutive days. The task which is on the critical path is now at risk tor delaying the
schedule. What should the project manager do?
Show answerHide answer
Correct answer: CAsk the team member if there is an impediment and help to remove the blockers
Question 276Choose 1
A project manager is working on the delivery of a solution that needs to be deployed to the
public quickly. The project team is experienced, the stakeholders are supporting the
delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?
Show answerHide answer
Correct answer: AHave a high-level plan for incremental deliveries and get the customer's feedback as
early as possible.
Question 277Choose 1
In experienced project manager has never managed an agile project until now. Due to the
uncertainty of the project, the project manager is struggling with the definition of the project
scope and is taking a long time trying to define it.
What should the project manager do?
Show answerHide answer
Correct answer: CStart executing the project as the scope will be defined and redefined throughout the
project.
Question 278Choose 1
An agile team completes a deliverable that is to be certified by another expert team The
second team does not take the deliverable for many months What should the servant
leader do?
Show answerHide answer
Correct answer: AReview the process and remove the impediment
Question 279Choose 1
A project manager is evaluating a project and realizes that its earned value (EV) shows the
cost spent is higher than the value delivered. The project manager then discovers that the
team has been adding small features that are not part of the requirements.
What should the project manager do?
Show answerHide answer
Correct answer: AAsk the team to focus on and deliver only the agreed-upon features.
Question 280Choose 2
After months of careful planning and discussions with subject matter experts (SMEs). a
new law is announced that may significantly impact the project budget. What should the
project manager do first?
Show answerHide answer
Correct answer: A, DConsult the risk and issue logs.Discuss with the project sponsor.