Question 271 Choose 1
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?
Show answerHide answer

Correct answer: B Review this method with the team.

Question 272 Choose 1
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?
Show answerHide answer

Correct answer: B Contact a subject matter expert (SME) for advice and consultation.

Question 273 Choose 1
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?
Show answerHide answer

Correct answer: C Work with the team to determine appropriate project methods and practices and implement them.

Question 274 Choose 1
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?
Show answerHide answer

Correct answer: B Suggest using an agile approach since customer and team collaboration is critical for project success.

Question 275 Choose 1
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
Show answerHide answer

Correct answer: C Ask the team member if there is an impediment and help to remove the blockers

Question 276 Choose 1
A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?
Show answerHide answer

Correct answer: A Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

Question 277 Choose 1
In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?
Show answerHide answer

Correct answer: C Start executing the project as the scope will be defined and redefined throughout the project.

Question 278 Choose 1
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
Show answerHide answer

Correct answer: A Review the process and remove the impediment

Question 279 Choose 1
A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?
Show answerHide answer

Correct answer: A Ask the team to focus on and deliver only the agreed-upon features.

Question 280 Choose 2
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
Show answerHide answer

Correct answer: A, D Consult the risk and issue logs.Discuss with the project sponsor.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt