A project team has finished participating in an iterative product increment planning session.
After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated
requirements?
Show answerHide answer
Correct answer: CEnsure every user story has acceptance criteria.
Question 262Choose 1
A project team identified a low-cost software product available for purchase that would
drastically reduce the scope of development. The development manager has confirmed
that this tool would fulfill the business need.
What should the project manager do?
Show answerHide answer
Correct answer: DRecommend the option to the product owner for consideration.
Question 263Choose 1
A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?
Show answerHide answer
Correct answer: DSchedule a meeting with the provider to collaborate on the options
Question 264Choose 1
A project manager is leading a project that involves on-site and remote team members One
task that was assigned to a team member in another country appears to be behind
schedule When the project manager inquires about this, the team member claims that the
task was completed and that this was reported to the team lead via a telephone
conversation
What should the project manager do?
Show answerHide answer
Correct answer: CReview this issue with the team lead for possible ways to resolve this situation
Question 265Choose 1
An agile project is in the seventh iteration with multiple changes being accommodated from
the project start due such as regulatory changes technological innovations market
competition and other changes What should the project manager do to manage these
continuous changes coming into the project?
Show answerHide answer
Correct answer: CAccommodate the critical and urgent changes in the current iteration
Question 266Choose 1
A project is almost completed, and both the sponsor and the project management office
(PMO) are happy with the project manager's performance reviews. The project manager is
under budget and ahead of schedule. However, a team member asks to add a feature to
the product that will make the product more impressive and acceptable to the end users.
What should the project manager do first?
Show answerHide answer
Correct answer: BDetermine if the feature is within the scope.
Question 267Choose 1
A project manager is asked to develop maintenance planning software for a power plant. A
similar project was executed by another department in the organization that was later
closed due to low performance. The project manager is concerned about the project's
performance and wants to
take action in advance to ensure the project succeeds.
What should the project manager do?
Show answerHide answer
Correct answer: DReview the lessons learned on similar projects so that they do not fall back into the
same pattern.
Question 268Choose 1
A project manager is working on a project that will transform the organization's operating
model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager
proceed?
Show answerHide answer
Correct answer: CAllocate the budget to the deliveries that have higher business value for the organization
than those with lower business value.
Question 269Choose 1
A key stakeholder has recently started in a company and has been assigned to a hybrid
project. Although very experienced in their domain, the stakeholder has only been exposed
to predictive project approaches.
What should the project manager do?
Show answerHide answer
Correct answer: DAllocate time to mentor the stakeholder in the selected project approach.
Question 270Choose 1
A project manager for a large software delivery project is in the process of finalizing the
project governance, The project manager would like to implement procedures that do not
align with several policies required by the organization's project management office (PMO).
The project manager
believes that the procedures outlined in the project governance will be necessary for this
particular project due to the unique nature of the technology.
What should the project manager do?
Show answerHide answer
Correct answer: CDiscuss the proposed changes with the PMO
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.