Question 261 Choose 1
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?
Show answerHide answer

Correct answer: C Ensure every user story has acceptance criteria.

Question 262 Choose 1
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?
Show answerHide answer

Correct answer: D Recommend the option to the product owner for consideration.

Question 263 Choose 1
A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?
Show answerHide answer

Correct answer: D Schedule a meeting with the provider to collaborate on the options

Question 264 Choose 1
A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation

What should the project manager do?
Show answerHide answer

Correct answer: C Review this issue with the team lead for possible ways to resolve this situation

Question 265 Choose 1
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
Show answerHide answer

Correct answer: C Accommodate the critical and urgent changes in the current iteration

Question 266 Choose 1
A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?
Show answerHide answer

Correct answer: B Determine if the feature is within the scope.

Question 267 Choose 1
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds.

What should the project manager do?
Show answerHide answer

Correct answer: D Review the lessons learned on similar projects so that they do not fall back into the same pattern.

Question 268 Choose 1
A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?
Show answerHide answer

Correct answer: C Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

Question 269 Choose 1
A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?
Show answerHide answer

Correct answer: D Allocate time to mentor the stakeholder in the selected project approach.

Question 270 Choose 1
A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO).

The project manager believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the technology.

What should the project manager do?
Show answerHide answer

Correct answer: C Discuss the proposed changes with the PMO

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt