An agile project manager has just been given a sizeable software development project to
implement. Early in the initiation stage, the project sponsor requests an indication of time
lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
The marketing team is moving from predictive to hybrid approaches for their projects. The
marketing director is not familiar with hybrid approaches and does not support the new
direction. What should the project manager do?
Show answerHide answer
Correct answer: CTrain the marketing team and keep their director informed.
Question 243Choose 1
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager
wants to fix this issue immediately.
Why is this situation problematic?
Show answerHide answer
Correct answer: CThe project manager is obligated to comply with the project location's
regulatoryrequirements.
A solution designer in an agile team often passes the design information to team members
without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
Show answerHide answer
Correct answer: BReview the process that resulted in this situation.
Question 245Choose 1
project manager for a defense software application has a culturally and gender-diverse
team with a short project time line Considering the project will be stressful what skill should
the project manager use to monitor the team's performance?
Show answerHide answer
Correct answer: CEmotional intelligence
Question 246Choose 1
A few virtual team members are located in a region that generally has good internet
connectivity. However, they frequently experience connectivity
issues joining team calls during the day.
What should the project manager do?
Show answerHide answer
Correct answer: DDetermine what the problem is and develop an action plan.
Question 247Choose 1
A project manager works for a large global company. The project manager is leading a
project where the expected business value is to improve the company's image and
reputation. During the project's closing phase, the project manager realizes that there is still
a negative perception about the company's brand.
What should the project manager have done to prevent this?
Show answerHide answer
Correct answer: AMonitored progress in achieving the business value throughout the project
Question 248Choose 1
A project manager is assigned to a project that has a tight schedule. Due to recent market
changes the marketing team has identified that a few features that were initially in the
scope are no longer required
What should the project manager do?
Show answerHide answer
Correct answer: DReview the change request with the project stakeholders and evaluate the impact of the
scope reduction
Question 249Choose 1
A final iteration is underway and a project team is about to complete development Planning
tot the product release is about to start. One stakeholder raised a concern about the
product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
Show answerHide answer
Correct answer: AAssess the business value impact and review the product roadmap to include any
changes
Question 250Choose 1
A project manager works at an organization that intends to use an agile delivery approach,
The product owner asks the project manager what the benefit of agile delivery is from a
project evaluation perspective?
How should the project manager reply to the product owner?
Show answerHide answer
Correct answer: AThe functionality is delivered early; therefore, more value is delivered.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.