Question 241 Choose 1
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?
Show answerHide answer

Correct answer: D Backlog grooming, product backlog, minimum viable product (MVP)

Question 242 Choose 1
The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?
Show answerHide answer

Correct answer: C Train the marketing team and keep their director informed.

Question 243 Choose 1
A new project manager has been assigned to an environmental project. After reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?
Show answerHide answer

Correct answer: C The project manager is obligated to comply with the project location's regulatoryrequirements.

Question 244 Choose 1
A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?
Show answerHide answer

Correct answer: B Review the process that resulted in this situation.

Question 245 Choose 1
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
Show answerHide answer

Correct answer: C Emotional intelligence

Question 246 Choose 1
A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity issues joining team calls during the day.

What should the project manager do?
Show answerHide answer

Correct answer: D Determine what the problem is and develop an action plan.

Question 247 Choose 1
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?
Show answerHide answer

Correct answer: A Monitored progress in achieving the business value throughout the project

Question 248 Choose 1
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?
Show answerHide answer

Correct answer: D Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Question 249 Choose 1
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?
Show answerHide answer

Correct answer: A Assess the business value impact and review the product roadmap to include any changes

Question 250 Choose 1
A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?
Show answerHide answer

Correct answer: A The functionality is delivered early; therefore, more value is delivered.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt