A senior-level executive approached the project manager of a highly visible project that is
currently in the execution phase. The executive indicated that they do not support the
project
and will be actively trying to prevent its success by reailocating key team members to
another critical project.
What should the project manager do?
Show answerHide answer
Correct answer: BWork with the project sponsor to determine an appropriate response.
Question 252Choose 1
A servant leader is about to start a confidential agile research project. A high risk has been
identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
Show answerHide answer
Correct answer: AInclude this restriction as a ground rule and ensure all team members are familiar with it
by reviewing the ground rules at the end of everyiteration.
Question 253Choose 1
A project manager is a part of the project management office (PMO) and Is tasked with
finding a reputable vendor to provide on-site support for their project. The project sponsor
stresses the urgency of the need and suggests using a vendor they know to provide the
support.
What should the project manager do given the urgency?
Show answerHide answer
Correct answer: DFollow the company's standard vendor selection criteria process,
Question 254Choose 1
A project manager has been assigned to handle a company’s newest product. The product
is in the conceptual stages and no one is sure about the success or marketability of the
product. Management wants to deliver the product in 3 months.
What should the project manager do next?
Show answerHide answer
Correct answer: AExplore the minimum requirements of the product and their feasibility.
Question 255Choose 1
Due to a statewide emergency, a project team for a global insurance company is being
forced to complete a project virtually, The project manager is tasked with conducting
meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
Show answerHide answer
Correct answer: BUse a password-enabled audio/video product,
Question 256Choose 1
An agile project team is tasked with a new project After multiple discussions with me
customer it appears that there is a lack of clarity on the requirements which resulted in
delays in the architecture and design phase
What should the team do next?
Show answerHide answer
Correct answer: CStart with the product prototype development, review with the customer, and gather
feedback
Question 257Choose 2
A company is implementing a project with team members who are located in different
countries and lime zones Performance assessments show that team performance is low
because the team doesn't have a common understanding about task distribution
What should the project manager do?
Show answerHide answer
Correct answer: B, DPerform team-building activitiesRevisit the communications management plan
Question 258Choose 1
A company initiated a departmental transformation project improving the processes for the
organization using a predictive approach, This is a critical project for the organization and,
in the middle of the project, the project manager noticed that one of the deliverables cannot
be produced due to a missing technical skill.
What should the project manager have done to avoid this?
Show answerHide answer
Correct answer: CIdentified all required skills during the planning of the project
Question 259Choose 1
A project manager is leading a project to modemize the information technology of a bank.
The project manager needs to determine how the project stakeholders should
communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
Show answerHide answer
Correct answer: CUse a variety of communication methods that respect cultural, practical, and personal
preferences.
Question 260Choose 1
A major national company known for quality products has just selected a small
subcontracting firm to assist with a project. The project manager from the subcontracting
firm is meeting with the project team to ensure that the project is delivered according to the
customer's standards
in order to ensure this, what should the project manager define and document?
Show answerHide answer
Correct answer: DRequirements