Question 251 Choose 1
A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?
Show answerHide answer

Correct answer: B Work with the project sponsor to determine an appropriate response.

Question 252 Choose 1
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?
Show answerHide answer

Correct answer: A Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

Question 253 Choose 1
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?
Show answerHide answer

Correct answer: D Follow the company's standard vendor selection criteria process,

Question 254 Choose 1
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?
Show answerHide answer

Correct answer: A Explore the minimum requirements of the product and their feasibility.

Question 255 Choose 1
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?
Show answerHide answer

Correct answer: B Use a password-enabled audio/video product,

Question 256 Choose 1
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?
Show answerHide answer

Correct answer: C Start with the product prototype development, review with the customer, and gather feedback

Question 257 Choose 2
A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?
Show answerHide answer

Correct answer: B, D Perform team-building activitiesRevisit the communications management plan

Question 258 Choose 1
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?
Show answerHide answer

Correct answer: C Identified all required skills during the planning of the project

Question 259 Choose 1
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?
Show answerHide answer

Correct answer: C Use a variety of communication methods that respect cultural, practical, and personal preferences.

Question 260 Choose 1
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?
Show answerHide answer

Correct answer: D Requirements

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt