Question 231 Choose 1
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9
Show answerHide answer

Correct answer: C Request a meeting with the disruptive team member and help to resolve the issue

Question 232 Choose 1
A subcontractor informs the project manager that they are unable to supply a key component to the project. What should the project manager do?
Show answerHide answer

Correct answer: D Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Question 233 Choose 1
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?
Show answerHide answer

Correct answer: B Submit a change request through the Integrated change control process.

Question 234 Choose 1
A team member is openly criticized by others during a standup meeting for failing to complete yesterday's tasks. What should the agile coach do first to address the situation?
Show answerHide answer

Correct answer: A Emphasize the ground rules and then focus on today's activities and impediments.

Question 235 Choose 1
A customer calls the project manager to express concern about a project team member who has been making changes within the live environment without approval. The team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?
Show answerHide answer

Correct answer: A Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.

Question 236 Choose 1
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?
Show answerHide answer

Correct answer: D Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Question 237 Choose 1
A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
Show answerHide answer

Correct answer: D Use the project management information system (PMIS) to share information.

Question 238 Choose 1
A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?
Show answerHide answer

Correct answer: D During each iteration and review

Question 239 Choose 1
Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack of clarity on processes and the project manager's relationship with company B.

What should the project manager do to resolve this conflict?
Show answerHide answer

Correct answer: D Work with the team to analyze which processes are suitable to use and define them inthe ground rules.

Question 240 Choose 1
An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?
Show answerHide answer

Correct answer: D Reevaluated the new product owner's needs for better engagement

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt