A project manager is planning a project to build a research center with the installation of
scientific equipment. Since the research topic is new and unfamiliar, the equipment
required might change during project execution.
How should the project manager plan this project?
Show answerHide answer
Correct answer: AUse a different project life cycle approach for the different parts of this project by
adopting a hybrid approach.
Question 42Choose 1
A high-tech borehole project was initiated with the goal of providing water for a rural
community of 1500 villagers located in an arid region. The project was completed with a
cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six
months after its completion, it is determined that the villagers could not access water.
What caused this situation to occur?
Show answerHide answer
Correct answer: BThe requirements gathering was inadequate.
Question 43Choose 3
A project team is experiencing communication issues during project execution. The project
manager realizes that the communications management plan needs to be reviewed.
Which are three fundamental actions the project manager should take? (Choose 3)
Show answerHide answer
Correct answer: A, C, DDecide on the frequency of communications.Determine the appropriate methods of communication.Identify the level of detail needed by different stakeholders.
Question 44Choose 1
A project to support an organizational transformation is in the planning phase.
Transformation is the project sponsor's idea and is not aligned with key stakeholders
because they all have different opinions about the project outcomes.
What should the project manager do next?
Show answerHide answer
Correct answer: DConduct a workshop on project goals and deliverables with the key stakeholders.
Question 45Choose 1
A project manager was assigned to lead a global project with a virtual team that is globally
dispersed. The project manager has difficulties communicating with the team members and
there seems to be frequent misunderstandings and conflicts.
What should the project manager do?
Show answerHide answer
Correct answer: CListen to team members actively and change the communication practices accordingly.
Question 46Choose 3
A project manager is new to an organization that typically follows a hybrid approach but is
shifting to incorporate more agile. A dedicated project team has been provisionally
assigned. The new project manager needs to review the internal environment in order to
build a high-performing team.
To build a high-performing team, which three factors should the project manager evaluate?
(Choose 3)
Show answerHide answer
Correct answer: A, B, EReview the team's capability to determine if they have the skill set needed to proceed
forward.Evaluate the infrastructure to determine if the team has the appropriate equipment and
communication channels.Assess the organizational culture to determine if more needs to be done to foster
psychological safety.
Question 47Choose 1
A compliance manager announces a new policy issued by the government that may impact
project development.
How should the project manager respond?
Show answerHide answer
Correct answer: CAddress any blockers to the project due to this policy and resolve them.
Question 48Choose 1
A company is transitioning from using a predictive approach to using an agile framework on
a project. The project sponsor is concerned about the level of uncertainty and how to
determine the time and budget required to complete the scope.
What should the project manager do to address this situation?
Show answerHide answer
Correct answer: BAsk the project team to create a high-level budget baseline for the project and provide
more detail only for the first project stages.
Question 49Choose 1
Negotiations are underway to secure an agreement with a critical supplier for the project.
The negotiation situation has become contentious as it is becoming apparent that both
parties will not receive everything they want and that a compromise might be necessary to
avoid project delays, cost overruns, and damage to reputations.
What should the project manager do to help ensure a successful outcome for the project?
Show answerHide answer
Correct answer: ACollaborate with stakeholders to complete an analysis of priorities with ranked
objectives.
Question 50Choose 2
A project lead was asked to support the team by subdividing the project tasks as necessary
to help define the minimum viable product (MVP).
Which two steps should the project lead take to define the MVP? (Choose 2)
Show answerHide answer
Correct answer: D, EConduct an information gathering session to determine the project value.Refer to the stakeholder register to determine who should be consulted.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.