PMI certification · Exam PMP

PMP Mock Exam Page 4

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 7: Exam Pool G, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 7: Exam Pool G questions

31–40 of 82 free
Question 31 Choose 1
A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?
Show answerHide answer

Correct answer: B Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

Question 32 Choose 1
A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?
Show answerHide answer

Correct answer: C Arrange a required training session for the team member.

Question 33 Choose 1
During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?
Show answerHide answer

Correct answer: C Record the situation in the issue log immediately and evaluate the impact of losing the resource.

Question 34 Choose 1
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
Show answerHide answer

Correct answer: D Establish a common language of terms with which to communicate with the provider.

Question 35 Choose 1
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?
Show answerHide answer

Correct answer: C Reach out to the team member to discuss and address their concerns as soon as possible.

Question 36 Choose 1
An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?
Show answerHide answer

Correct answer: B Kanban board

Question 37 Choose 1
To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?
Show answerHide answer

Correct answer: C Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.

Question 38 Choose 1
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
Show answerHide answer

Correct answer: A Submit a request to access contingency reserves and accept the changes.

Question 39 Choose 2
An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)
Show answerHide answer

Correct answer: A, E Communicate via email to the project's email distribution group.Communicate verbally to the key project stakeholders.

Question 40 Choose 1
A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?
Show answerHide answer

Correct answer: C An agile approach is easily adaptable.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt