PMI certification · Exam PMP

PMP Mock Exam Page 8

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 7: Exam Pool G, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 7: Exam Pool G questions

71–80 of 82 free
Question 71 Choose 1
A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?
Show answerHide answer

Correct answer: B Partner with a company that is an expert in this area.

Question 72 Choose 1
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
Show answerHide answer

Correct answer: D Ask the team to work on the unblocked deliverables.

Question 73 Choose 3
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)
Show answerHide answer

Correct answer: B, D, E Ask the testers to provide additional information.Continue with testing according to the plan.Brainstorm the issue with the project team.

Question 74 Choose 1
A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.

What should the project lead do?
Show answerHide answer

Correct answer: B Build a task board on a large wall using sticky notes.

Question 75 Choose 1
Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?
Show answerHide answer

Correct answer: B Create a responsible, accountable, consulted, informed (RACI) chart.

Question 76 Choose 1
A project manager is in the process of authoring the communications management plan for a new project. One of the project's stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.

What should the project manager do?
Show answerHide answer

Correct answer: B Ensure that sensitive information is not included in stakeholder updates.

Question 77 Choose 1
A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?
Show answerHide answer

Correct answer: C Refer to the risk register and follow the mitigation plan.

Question 78 Choose 1
A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?
Show answerHide answer

Correct answer: C Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.

Question 79 Choose 1
An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?
Show answerHide answer

Correct answer: C Coach the team to be more inclusive.

Question 80 Choose 1
A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.

What should the project manager do?
Show answerHide answer

Correct answer: B Ask the team and product owner to reprioritize the user stories in the backlog for an updated iteration schedule.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt