A project manager works for an IT consulting firm that has submitted a bid during the
request for proposal (RFP) process for a contract that focuses on data center migration and
optimization. However, the consulting firm has little experience in data center optimization.
What should the project manager do?
Show answerHide answer
Correct answer: BPartner with a company that is an expert in this area.
Question 72Choose 1
A project is on its third iteration out of nine. During the daily meetings, the project team
realizes that some deliverable approvals are delayed because a key stakeholder is out of
the office.
Show answerHide answer
Correct answer: DAsk the team to work on the unblocked deliverables.
Question 73Choose 3
Three testers joined the project team just before the end of the build. During the project
team meeting, the testers indicated that the project quality is poor, and they should not
continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose 3)
Show answerHide answer
Correct answer: B, D, EAsk the testers to provide additional information.Continue with testing according to the plan.Brainstorm the issue with the project team.
Question 74Choose 1
A product owner is complaining about the team's performance. The developers are highly
skilled, and most of the issues were caused by dependencies. The developers provide a
formal status report every day, but it is clear that the other team members are not satisfied
with this.
What should the project lead do?
Show answerHide answer
Correct answer: BBuild a task board on a large wall using sticky notes.
Question 75Choose 1
Before kicking off a high-priority and complex project, what should the project manager do
to ensure all project stakeholders are aware of their role scope as it relates to project
activities?
Show answerHide answer
Correct answer: BCreate a responsible, accountable, consulted, informed (RACI) chart.
Question 76Choose 1
A project manager is in the process of authoring the communications management plan for
a new project. One of the project's stakeholders has a habit of posting work updates on
social media, which may include confidential project status updates.
What should the project manager do?
Show answerHide answer
Correct answer: BEnsure that sensitive information is not included in stakeholder updates.
Question 77Choose 1
A project is late due to a large number of scope changes. This was raised as a risk in the
risk register during the initiation phase. The team is afraid that they will be blamed in case
of failure and recommends that the project manager ask for an extension.
What should the project manager do first?
Show answerHide answer
Correct answer: CRefer to the risk register and follow the mitigation plan.
Question 78Choose 1
A project manager is leading a project with a team that is comprised of both experienced
and inexperienced team members. What should the project manager do to ensure an
effective project team?
Show answerHide answer
Correct answer: CIdentify how the team members with no experience can contribute according to their
capabilities and provide training if needed.
Question 79Choose 1
An agile team is struggling to successfully deliver what they have committed. During the
daily status meetings, the project manager notices that the most senior engineer is doing
all of the talking, leaving little time for the other members to share their status. The team's
performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
Show answerHide answer
Correct answer: CCoach the team to be more inclusive.
Question 80Choose 1
A project manager assigned to an agile project realizes that after iteration demos, new user
stories to fix issues reported by the product owner are not included in prioritization of the
following sprint. This has led to a high number of unprioritized stories in the backlog and
will lead to delay of the product release.
What should the project manager do?
Show answerHide answer
Correct answer: BAsk the team and product owner to reprioritize the user stories in the backlog for an
updated iteration schedule.