A project manager has been assigned to a new project. The project sponsor has requested
a detailed timeline, but the project includes some deliverables that are not yet clearly
defined.
Which project management approach should the project manager advise using?
Show answerHide answer
Correct answer: CAs the project appears to have both agile and predictive elements, a hybrid approach is
the best option.
Question 52Choose 1
During a planning session, the development team and the product owner are arguing about
the effort needed to deliver a specific feature in a software development project. The
product owner says that the feature can be developed in one week, whereas the team
estimates that it will take at least two weeks. After several hours of discussion, they have
not reached an agreement.
What should the project lead do?
Show answerHide answer
Correct answer: DEducate the product owner that the project team members are the most appropriate
group for assessing the effort.
Question 53Choose 1
A project manager is working on a global project and realizes that one team member is not
performing as expected. The project manager meets with the team member to find out
what is causing this low performance. The project manager discovers the team member is
experiencing conflict and feels uncomfortable with the team. The team member then asks
to be moved to another project.
What should the project manager do?
Show answerHide answer
Correct answer: ARequest human resources (HR) to help.
Question 54Choose 1
A project manager is quantifying risk for their project. The project manager needs an expert
opinion in this process, but experts are spread over different geographic locations and time
zones.
What should the project manager do?
Show answerHide answer
Correct answer: CUse the Monte Carlo analysis online.
Question 55Choose 1
During a project's stakeholder identification stage, team members are struggling to identify
the level of influence for two stakeholders. One is considered important, while the second is
not quite as important as the first one. For this project, stakeholder engagement is a critical
activity.
What should the project manager do?
Show answerHide answer
Correct answer: DConduct an evaluation on both stakeholders.
Question 56Choose 1
A new employee has joined the management team and wants to get a quick overview of all
the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?
Show answerHide answer
Correct answer: AReview the information radiators for each project.
Question 57Choose 1
A project manager received several complaints from different project team members
related to an unnecessary additional step the functional lead implemented as a preference.
The project team members' work has been affected by this and they have missed a few
deadlines.
What should the project manager do to address this concern?
Show answerHide answer
Correct answer: CAsk the functional lead to remove this additional step as it is not vital to the project.
Question 58Choose 1
A project is starting its first iteration out of six. During one of the daily meetings, the project
manager realized that one of the team members does not have experience working in agile
environments.
What should the project manager do?
Show answerHide answer
Correct answer: BAssign an agile mentor and follow the training process.
Question 59Choose 1
A project team is currently dispersed across multiple countries and time zones. Recent
team feedback shows engagement levels are sub-optimal, and information flows are
irregular and one-sided. There are also company travel restrictions in place, preventing
physical colocation.
What improvements should the project manager implement to improve engagement?
Show answerHide answer
Correct answer: BConfirm with the team which approach works best for exchanging information.
Question 60Choose 1
A project manager's project relies on services from a department that has a new leader.
Since the new leader was appointed, the services from their department have been slow
which threatens the project's delivery deadline.
What should the project manager do?
Show answerHide answer
Correct answer: DArrange a meeting with the leader to explain the project's needs and understand the
leader's perspective.