Question 11 Choose 1
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?
Show answerHide answer

Correct answer: C Evaluate contract and administrative tasks.

Question 12 Choose 1
A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team's workload effectively?
Show answerHide answer

Correct answer: B Encourage open communication and involve the team in task distribution decisions.

Question 13 Choose 1
Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?
Show answerHide answer

Correct answer: B Verify the critical path of the consolidated project schedule.

Question 14 Choose 1
During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?
Show answerHide answer

Correct answer: B Approach the product owner to determine the next course of action and update the backlog.

Question 15 Choose 1
The team's work assignments have been generically distributed. A new team member is performing slower than expected.

What should the project manager do?
Show answerHide answer

Correct answer: D Assess the new team member's skills in order to determine additional training needs.

Question 16 Choose 1
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
Show answerHide answer

Correct answer: A Seek to understand the sentiments of each team member and then work with them to address their concerns.

Question 17 Choose 1
A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?
Show answerHide answer

Correct answer: B Discuss the need to increase productivity with the contractor.

Question 18 Choose 3
The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)
Show answerHide answer

Correct answer: A, D, E Leverage the project governance system to track and manage the project artifacts.Ensure the project artifacts are kept up to date and accessible to all stakeholders.Work with the team to determine the process to manage the project artifacts.

Question 19 Choose 1
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?
Show answerHide answer

Correct answer: D Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

Question 20 Choose 1
During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?
Show answerHide answer

Correct answer: D Meet with the team members to discuss the priority of the project schedule.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt