A project manager is leading the construction of a branch office building for a national
bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
Show answerHide answer
Correct answer: CEvaluate contract and administrative tasks.
Question 12Choose 1
A project manager's team has been working very hard to meet a critical deadline. Some
project team members are experiencing burnout due to the high workload.
What should the project manager do first to manage the team's workload effectively?
Show answerHide answer
Correct answer: BEncourage open communication and involve the team in task distribution decisions.
Question 13Choose 1
Multidisciplinary teams will be needed for a project. The project manager asks the project
planner to create a consolidated schedule. The project manager determines from the
consolidated schedule that the project's finish date exceeds the requested finish date.
What should the project manager suggest to the planner to analyze this issue?
Show answerHide answer
Correct answer: BVerify the critical path of the consolidated project schedule.
Question 14Choose 1
During a sprint, the team is experiencing conflict because the customer asks for additional
features that increase the complexity. The scrum master is trying to resolve the conflict.
Which approach should the scrum master use?
Show answerHide answer
Correct answer: BApproach the product owner to determine the next course of action and update the
backlog.
Question 15Choose 1
The team's work assignments have been generically distributed. A new team member is
performing slower than expected.
What should the project manager do?
Show answerHide answer
Correct answer: DAssess the new team member's skills in order to determine additional training needs.
Question 16Choose 1
A project team is not motivated and is producing the bare minimum. The team has no
interest in keeping pace with the aggressive project schedule.
Show answerHide answer
Correct answer: ASeek to understand the sentiments of each team member and then work with them to
address their concerns.
Question 17Choose 1
A project is on schedule. However, during a site visit, a project manager notices that the
contractor's productivity is low.
What should the project manager do?
Show answerHide answer
Correct answer: BDiscuss the need to increase productivity with the contractor.
Question 18Choose 3
The project manager is planning a project with several legal aspects for the city's
municipality. The project is expected to take a year and will require a lot of paperwork since
it involves multiple stakeholders, including the city's court.
What three actions should the project manager do? (Choose 3)
Show answerHide answer
Correct answer: A, D, ELeverage the project governance system to track and manage the project artifacts.Ensure the project artifacts are kept up to date and accessible to all stakeholders.Work with the team to determine the process to manage the project artifacts.
Question 19Choose 1
Following an investment decision-making meeting for a project, a change to the
organizational structure takes place in a multinational company. Due to the organizational
change, internal stakeholders are referring the project manager to various other personnel
for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
Show answerHide answer
Correct answer: DObtain the latest organizational chart and send an email to the appropriate person
requesting budget approval.
Question 20Choose 1
During a daily meeting of a challenging project, two team members started to argue on the
preferred solution based on their assumptions. The situation prevented the progress to the
next phase of development, which could impact the finish date of the project.
What should the project manager do next?
Show answerHide answer
Correct answer: DMeet with the team members to discuss the priority of the project schedule.