A scrum master is receiving conflicting status updates for the same task. How should an
accurate status be obtained from the team?
Show answerHide answer
Correct answer: BEstablish a clear definition of done (DoD) for each task.
Question 62Choose 1
An important project to build a new airport was suddenly stopped because of the
complaints from residents in the surrounding communities. The residents stated that they
were not consulted and that the project would cause ecological and pollution damage.
What should that project manager have done first in order to avoid this situation?
Show answerHide answer
Correct answer: AIdentified the stakeholders and their expectations
Question 63Choose 1
At the first retrospective meeting, a developer in a newly formed team points out that
frequent delays in documenting the requirement solution are impacting the workflow. The
developer wants to know why the analyst is not doing their job on time. Confronting the
analyst causes a conflict that quickly escalates. The analyst is certain that the
documentation process is not solely their function.
What should the project manager do to resolve the conflict and prevent future conflicts as
the team matures?
Show answerHide answer
Correct answer: CClarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).
Question 64Choose 1
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
Show answerHide answer
Correct answer: BAsk the project management office (PMO) for guidance.
Question 65Choose 1
Two project team members are having difficulty communicating updates and issues. One
team member prefers telephone calls for any kind of urgency, whereas the other team
member prefers email communication. This difference results in a lack of understanding
between the team members and sometimes hinders timely communication.
What should the project manager do?
Show answerHide answer
Correct answer: CAsk the team members to follow the ground rules in the project management plan.
Question 66Choose 1
A project manager assembled a team of 10 developers. Because the organization did not
have a development team for this project, contractors were hired. In the kick-off meeting,
one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?
Show answerHide answer
Correct answer: DRecommend that the team develop their own guidelines.
Question 67Choose 1
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is
trending downward. To maintain on-time completion, the scrum master needs to add 30
additional team members in the next month to enable more sprints. The project manager is
concerned because the schedule performance index (SPI) is 1.0.
What is the first step the project manager should take?
Show answerHide answer
Correct answer: BQuantify the cost for the 30 team members and determine if there is budget available to
fund the expanded team.
Question 68Choose 1
A project manager leads an agile development project. During the sprint planning meeting,
the development team expresses concerns that the proposed scope of the next sprint is
much larger than expected given the current resource allocation. The project manager
believes the scope is essential to meet the project milestones.
How should the project manager approach negotiating an agreement with the team to
ensure the project remains on track?
Show answerHide answer
Correct answer: BSuggest prioritizing the most critical features for the next sprint as well as reevaluating
the remaining scope.
Question 69Choose 1
A project team member who has the expert knowledge necessary for the project is often
absent from meetings. The team member sends a message to the project manager
questioning them about the rationale behind some decisions made on the project.
How should the project manager handle the situation?
Show answerHide answer
Correct answer: BSchedule a meeting to review the team member's concerns and revisit the decisions if
required.
Question 70Choose 1
A project manager is overseeing a 10-mile piping installation project that was supposed to
spend US$15,000 per mile of piping installation and should complete the project exactly 20
weeks from its start. The project manager just found out that only 80% of the work has
been completed.
What is the budget at completion (BAC)?
Show answerHide answer
Correct answer: BUS$150,000