A project is ending its fifth out of six iterations. During the iteration review, a customer adds
a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?
Show answerHide answer
Correct answer: DEstimate the impact and consult with the product owner.
Question 62Choose 1
A key stakeholder who is highly involved in the project claims that the reports sent by the
project team are inadequate. What should the project manager do first?
Show answerHide answer
Correct answer: DEnsure that the reports comply with the communications management plan.
Question 63Choose 1
A project manager assigned to an education project needs to train a workforce in
application development. The customer is responsible for
providing the training center, and the deadline to start the first training is in 2 weeks. The
customer calls to say that the center will not be available
in 2 weeks due to some unforeseen problems.
What should the project manager do next?
Show answerHide answer
Correct answer: CHelp the customer find an alternative location to start the training.
Question 64Choose 1
At the end of a project's initiation phase, the budget was developed and sent to the
approval board. During the approval meeting, one of the key stakeholders asked how the
budget was developed for future uncertainties.
How should the project manager reply?
Show answerHide answer
Correct answer: BProbabilistic analysis was used to develop the budget to address future uncertainties.
Question 65Choose 3
A new project team consists of team members from different departments who have
varying levels of experience and different areas of expertise.
Which three approaches should the project manager take in order to facilitate knowledge
sharing? (Choose 3)
Show answerHide answer
Correct answer: A, B, EArrange a daily learning session for project team members during lunch to facilitate
knowledge transfer.Allow each team member time in the retrospective sessions to share a little bit about
their role and areas of knowledge.Schedule shadowing sessions among team members to facilitate team learning.
Question 66Choose 1
A project manager is looking for ways to keep the budget on track throughout the project life cycle.
What should the project manager do to ensure that happens?
Show answerHide answer
Correct answer: DUse metrics to track the cost performance
Question 67Choose 1
A project manager was informed by their supplier that there will be an upcoming raw
material shortage due to a regulatory change. What should the project manager do?
Show answerHide answer
Correct answer: DAssess the possible impact of the raw material shortage on the project.
Question 68Choose 1
A team is focusing on quickly developing and shipping new product features due to very
aggressive market demands. The team is setting aside long-term work not directly related
to the current business objective, which affects product performance and generates more
customer support requests.
How can the team minimize the impact of the reduced focus on quality?
A project manager is assigned to work on a complex and innovative project. The
technology being used and developed is new and complicated, and most of the
stakeholders are unfamiliar with it.
Which approach should the project manager use as a servant leader?
Show answerHide answer
Correct answer: BAllocate resources to provide training about the new technology to the stakeholders.
Question 70Choose 1
During the execution phase of a project, a new department has been created in the
company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
Show answerHide answer
Correct answer: CPerform a stakeholder analysis and update the communications management plan to
reflect the new situation.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.