A project manager is working on a complex project with a high degree of change. What
strategy should the project manager use to ensure a
successful project completion?
Show answerHide answer
Correct answer: CIncrease the active engagement and participation of key stakeholders.
Question 82Choose 1
A project team is working on the design of a solution for a complex project. Due to a lack of
clarity of the customer's requirements, daily meetings
were agreed upon between the team and the customer. There are a few external
contractors in the project who do not agree with this idea as they
feel it is a waste of time.
What should the project manager do?
Show answerHide answer
Correct answer: AWelcome and involve the contractors as part of the project team.
Question 83Choose 1
A company just started managing a project using an agile approach. Due to this change,
the general manager is worried about the scope definition process for upcoming projects.
What should the project manager do to ensure the project scope is completely defined?
Show answerHide answer
Correct answer: BAsk for a budget increase to implement a double-check process to ensure every
business need is included in the requirements
Question 84Choose 1
Anew major road project is starting, and the contractor has contractually committed to
submitting regular status reports and participating in integration meetings. Halfway through
the project life cycle, the contractor stops participating in meetings and submitting reports,
stating these items consume too much time.
What should the project manager do first?
Show answerHide answer
Correct answer: CRemind the contractor that they committed to attending meetings and submitting reports
per the contract.
Question 85Choose 1
A project manager is implementing a project similar to a previous one that required strict
adherence to occupational health and safety (OHS). Both projects are for the same client
whose business environment is highly regulated. However, this time the client does not
appear to be concerned about OHS requirements.
What should the project manager do first?
Show answerHide answer
Correct answer: BDiscuss the OHS requirements with the client.
Question 86Choose 1
During a monthly review meeting, a high-performing team member raised a concern about
the quality feedback mechanism. The team member expressed that they are not able to
deliver high-quality output.
What should the project manager do first?
Show answerHide answer
Correct answer: DDiscuss this with the team and review the quality process.
Question 87Choose 1
A project requires the procurement of a large amount of equipment that needs to be on-site
before any other activity can begin. The procurement department has a lengthy approval
process.
What should the project manager do?
Show answerHide answer
Correct answer: AWork with the procurement team to find alternative options.
Question 88Choose 1
A project manager assigned team members to work in pairs on a large amount of technical
reports. At times, the project manager noticed that important information was not
shared properly among the team. This has caused delivery delays and, ultimately, the
failure to complete the project.
What is the root cause of this issue?
Show answerHide answer
Correct answer: CIncorrect communication techniques applied during implementation
Question 89Choose 1
An agile team has released the second version of its product, but the feedback is that the
software has many bugs that compromise the user experience. What should the
project manager do?
Show answerHide answer
Correct answer: AFacilitate the next retrospective meeting, focusing the team on analyzing root causes
and proposing solutions.
Question 90Choose 1
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,
Point A, which requires a significant cable length. The construction team found that the
power could be connected to Point B and save money.
What should the project manager do next?
Show answerHide answer
Correct answer: APerform a cost-benefit analysis to evaluate using the Point B option.