Question 51 Choose 1
A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?
Show answerHide answer

Correct answer: C Analyze the interests and influence of stakeholders and evaluate their requirements.

Question 52 Choose 1
A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?
Show answerHide answer

Correct answer: A Talk to the team member to determine why their performance changed.

Question 53 Choose 1
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months.

What should the project manager do to align stakeholders’ needs and expectations?
Show answerHide answer

Correct answer: A Work with the stakeholders to create a prioritized backlog and release a roadmap.

Question 54 Choose 1
A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?
Show answerHide answer

Correct answer: D Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

Question 55 Choose 1
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
Show answerHide answer

Correct answer: D Identify the risks in implementing the new technology.

Question 56 Choose 1
A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.

How should the project manager address this situation?
Show answerHide answer

Correct answer: C Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

Question 57 Choose 1
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?
Show answerHide answer

Correct answer: B Request the team to initiate a change request to execute the contract.

Question 58 Choose 1
A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.

How should the project manager address the customer's requests?
Show answerHide answer

Correct answer: D Explain to the customer that the project has been completed and enhancements will follow the change management process.

Question 59 Choose 1
A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
Show answerHide answer

Correct answer: B Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.

Question 60 Choose 1
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
Show answerHide answer

Correct answer: A Reach an agreement with the team on how to handle the situation.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt