A project manager is leading a large public project that will have a high impact on the
town's citizens. How should the project manager define the different requirements?
Show answerHide answer
Correct answer: CAnalyze the interests and influence of stakeholders and evaluate their requirements.
Question 52Choose 1
A project manager is managing a large project. During a review meeting, the project
manager discovers that one of the team members who use to be a high performer was not
able to complete their work on time.
What should the project manager do?
Show answerHide answer
Correct answer: ATalk to the team member to determine why their performance changed.
Question 53Choose 1
A project manager is in a cross-functional agile team. The project manager has been
assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to
meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
Show answerHide answer
Correct answer: AWork with the stakeholders to create a prioritized backlog and release a roadmap.
Question 54Choose 1
A company that uses a predictive approach and operates in a highly regulated market is
losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.
What approach should the project manager propose?
Show answerHide answer
Correct answer: DPropose a hybrid approach, leveraging the benefits of an agile approach while
respecting some aspects of the company’s industry.
Question 55Choose 1
A company plans to initiate a project involving a new technology. Approval for the project is
required. What should the project manager do?
Show answerHide answer
Correct answer: DIdentify the risks in implementing the new technology.
Question 56Choose 1
A team member who is working on a critical project deliverable reported that their computer
is not working. The IT department says that due to a high workload, they will not
be able to provide assistance for 1 week.
How should the project manager address this situation?
Show answerHide answer
Correct answer: CExplore options with the IT department to expedite the necessary repairs based on
criticality of the project.
Question 57Choose 1
A project team is executing a megaproject, and several contract requirements have been
identified. In the planning phase, the project team agreed that a contract would be
required 3 months prior to the project's finish date. During project execution, it was
determined that the contract was required immediately.
What should project manager do?
Show answerHide answer
Correct answer: BRequest the team to initiate a change request to execute the contract.
Question 58Choose 1
A project has recently completed its production go-live, meeting the project's completion
requirements in accordance with the scope document. However, the customer has been
requesting a number of significant project enhancements.
How should the project manager address the customer's requests?
Show answerHide answer
Correct answer: DExplain to the customer that the project has been completed and enhancements will
follow the change management process.
Question 59Choose 1
A project manager is planning a project with multiple work packages. Each work package
has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to
cover the resource costs of the project?
Show answerHide answer
Correct answer: BEstimate the costs at the work package level and add those costs to calculate the total
cost of the project and compare it to the allocated budget.
Question 60Choose 1
In the middle of an iteration, an agile team working on the development of a new product
was notified that an important team member will leave the project for a few weeks due to
some urgent personal issues. What should the project manager do regarding the activities
that were the responsibility of this team member?
Show answerHide answer
Correct answer: AReach an agreement with the team on how to handle the situation.