PMI certification · Exam PMP

PMP Mock Exam Page 10

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 6: Exam Pool F, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 6: Exam Pool F questions

91–100 of 143 free
Question 91 Choose 1
A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?
Show answerHide answer

Correct answer: A Explain to the team that open discussions are needed but remind the team to follow the ground rules.

Question 92 Choose 1
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?
Show answerHide answer

Correct answer: C Kanban board

Question 93 Choose 1
A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?
Show answerHide answer

Correct answer: C Review the options and possible solutions with the project team.

Question 94 Choose 1
In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project manager do next?
Show answerHide answer

Correct answer: D Produce a value-added product for the customer in each phase of the project.

Question 95 Choose 1
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
Show answerHide answer

Correct answer: C Organize more frequent sprint reviews with a broader audience.

Question 96 Choose 1
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.

What should the project manager do to resolve this conflict?
Show answerHide answer

Correct answer: D Communicate with the resource on the roles and responsibilities of this project.

Question 97 Choose 1
A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the company's core working hours begin at 9:00 a.m.

What should the project manager have done to prevent this situation?
Show answerHide answer

Correct answer: C Analyzed the boundaries of the negotiations for agreement

Question 98 Choose 1
A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?
Show answerHide answer

Correct answer: B Ask the existing team members to collaborate with the SME and complete the activity.

Question 99 Choose 1
A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?
Show answerHide answer

Correct answer: D The project manager and the project management team should select the appropriate artifacts for use in the specific project.

Question 100 Choose 1
A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion.

What should the project manager do?
Show answerHide answer

Correct answer: A Conduct a team activity to determine the reasons for this situation.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt