Question 41 Choose 1
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully. What should the project manager do to reduce the risk of project failure?
Show answerHide answer

Correct answer: D Provide team members with the necessary coaching and mentoring.

Question 42 Choose 1
During the execution of a project, a key stakeholder complains to the project manager about recent communications.

The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?
Show answerHide answer

Correct answer: D Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.

Question 43 Choose 1
A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?
Show answerHide answer

Correct answer: A Update the communications management plan to satisfy the client's request

Question 44 Choose 1
A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?
Show answerHide answer

Correct answer: D Work with relevant stakeholders to determine possible solutions.

Question 45 Choose 1
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?
Show answerHide answer

Correct answer: D Continue the meeting and use facilitation techniques to improve communication within the team.

Question 46 Choose 1
In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.

What should the project lead do?
Show answerHide answer

Correct answer: C Work with the product owner to change the priorities in the sprint backlog.

Question 47 Choose 1
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?
Show answerHide answer

Correct answer: D Work with the team to understand their views and add the appropriate dependencies and risks.

Question 48 Choose 1
A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?
Show answerHide answer

Correct answer: B Quality management plan

Question 49 Choose 1
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.

Which approach should the project manager use in this situation?
Show answerHide answer

Correct answer: A Hybrid approach

Question 50 Choose 1
A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources and has appointed a project manager.

What should the project manager recommend that the CEO do first?
Show answerHide answer

Correct answer: C Create a framework to support project success.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt