How can agile measurements improve upon predictive measurements in cases where the
final 10% of a project takes longer than planned?
Show answerHide answer
Correct answer: BBy focusing on the delivery of incremental working products lo the customer
Question 32Choose 1
A high-performing team is involved in a project with a new domain. The team is unable to
deliver as expected.
What should the project manager do?
Show answerHide answer
Correct answer: ASupport the team in identifying the area of development and address the gap.
Question 33Choose 1
A building management system (BMS) project is in its commissioning phase and handover
to the operations team will commence soon. However, the project manager noted
that both the project and operation teams are not able to properly operate the BMS. As a
result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
Show answerHide answer
Correct answer: BAllocated proper resources for training on BMS in the project plan
Question 34Choose 1
During the service procurement process for a strategic project, only one bidder submitted a
bid. The price of the offer is significantly large and the project sponsor is not convinced that
the return on investment (ROI) can be achieved.
How should the project manager address this issue?
Show answerHide answer
Correct answer: ARe-visit the project charter and seek other alternatives.
Question 35Choose 1
A project charter has been approved and the project manager has been assigned to the
project. The project manager is currently working with the project team to subdivide the
project work packages.
What is the project manager doing?
Show answerHide answer
Correct answer: CWork breakdown structure (WBS)
Question 36Choose 1
A project team is working on a company restructure that involves team member rotation.
There is a concern about how to execute the project within the schedule based on all of the
new team members.
What should the project manager do?
Show answerHide answer
Correct answer: CSet up a team alignment session to discuss the remaining work and contract with the
team.
Question 37Choose 2
In a fixed-budget project, the team has received a prioritized list of requirements and has
nearly completed the first iteration. The CEO has decided to redirect the team to focus on
creating a presentation for their upcoming technology summit. The CEO is not flexible
about this request.
Which two actions should the project manager take? (Choose 2)
Show answerHide answer
Correct answer: A, CRequest the CEO to assign some of the functional team members to work on the
presentation.Determine a new target completion date for the project based on the redirection of the
team.
Question 38Choose 1
A project team is transitioning from a predictive to an agile approach. The project manager
is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
Show answerHide answer
Correct answer: CEngage the operation teams in the retrospectives and demo sessions and incorporate
their feedback on project activities.
Question 39Choose 1
A multiyear resource constraint project is midway through the execution phase. During a
progress update meeting, it has been determined that there might be a schedule delay to
deliver the project. The project manager has observed that all of the team members are
working hard and lots of deliverables have already been completed.
What should the project manager do immediately about this situation?
Show answerHide answer
Correct answer: AAsk the project planner to identify the critical path and respective delayed activities, and
then investigate the reasons for the delay.
Question 40Choose 1
A project manager is leading a hybrid project that is building an app for a travel industry
startup. Due to unforeseen events, the features and the overall solution will not be useable
by many customers due to new travel restrictions.
What should the project manager do first?
Show answerHide answer
Correct answer: CAssess the environmental changes and recommend a pivot for the project.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.