Question 31 Choose 1
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
Show answerHide answer

Correct answer: B By focusing on the delivery of incremental working products lo the customer

Question 32 Choose 1
A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?
Show answerHide answer

Correct answer: A Support the team in identifying the area of development and address the gap.

Question 33 Choose 1
A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: B Allocated proper resources for training on BMS in the project plan

Question 34 Choose 1
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?
Show answerHide answer

Correct answer: A Re-visit the project charter and seek other alternatives.

Question 35 Choose 1
A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?
Show answerHide answer

Correct answer: C Work breakdown structure (WBS)

Question 36 Choose 1
A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.

What should the project manager do?
Show answerHide answer

Correct answer: C Set up a team alignment session to discuss the remaining work and contract with the team.

Question 37 Choose 2
In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)
Show answerHide answer

Correct answer: A, C Request the CEO to assign some of the functional team members to work on the presentation.Determine a new target completion date for the project based on the redirection of the team.

Question 38 Choose 1
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?
Show answerHide answer

Correct answer: C Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

Question 39 Choose 1
A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?
Show answerHide answer

Correct answer: A Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

Question 40 Choose 1
A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?
Show answerHide answer

Correct answer: C Assess the environmental changes and recommend a pivot for the project.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt