A project manager joins an existing project. One project stakeholder is unhappy with the
frequency and types of project updates received and has made a request for more What
should the project manager do next?
Show answerHide answer
Correct answer: BSchedule a meeting with the stakeholder to better understand their request
Question 22Choose 1
A project manager is working on a financial system implementation project for a
government company. One of the key stakeholders, who uses
predictive approaches, does not like virtual tools such as chats, task trackers, and so forth.
They prefer email, telephone calls, and face-to-face
meetings.
How should the project manager approach this situation?
Show answerHide answer
Correct answer: BAlign and agree with the stakeholder on the communication approach.
Question 23Choose 1
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the
project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a meeting with the project team and the key stakeholder as soon as possible
to discuss and agree on an approach.
Question 24Choose 1
A project being constructed in a remote rural area is nearing the end of construction. The
project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?
Show answerHide answer
Correct answer: DNewspapers
Question 25Choose 1
After the demo on a software project, one of the key stakeholders contacted the scrum
master and complained that they were unaware of changes made to the project. After
checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.
What should the scrum master do?
Show answerHide answer
Correct answer: DCheck the stakeholder register and ensure that every stakeholder's information is
correct and current.
Question 26Choose 1
A team working on a close deployment waits to receive critical information from the
customer. The customer keeps postponing sending the information which is delaying the
deployment.
What should the project manager have done to prevent the delay?
Show answerHide answer
Correct answer: AObtained all critical information ahead of time
Question 27Choose 1
A project manager is leading a software development project that will assist in maintenance
management for a power plant. The project manager is analyzing project performance data
and trying to forecast if the project will have any slippage in the future.
What should the protect manager do?
Show answerHide answer
Correct answer: CPerform trend analysis.
Question 28Choose 1
An agile team is in the early phases of the development cycle for a project; however, they
have already begun to deliver functionality to the customer. The team has identified risks to
the project and are working on developing the mitigation strategy.
What should the project manager do next?
Show answerHide answer
Correct answer: AIncorporate and prioritize the risks in the risk register according to impact.
Question 29Choose 1
An important national project is in (he execution phase. A time constraint activity must be
conducted on-site by a specialist from another country. Due to travel restrictions, the
specialist cannot perform the activity on-site. The activity cannot be completed without the
specialist's expertise. The project team is actively seeking assistance in order to complete
the job on time.
What should the project manager do to help the project team?
Show answerHide answer
Correct answer: BSchedule virtual sessions with the specialist to guide the team in completing the activity.
Question 30Choose 1
A company has started developing a new product. During execution the project team
notices that another competitor has launched a product with very similar functionalities and a cheaper market price.
What should have been done differently to avoid this scenario?
Show answerHide answer
Correct answer: AA minimum viable product (MVP) should have been released to get feedback from the
market.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.