A team has been working for some time on a project with incremental deliveries. The
project manager noticed that one of the team members is less engaged in team meetings,
yet delivers promptly. While discussing the source of demotivation, the team member
informed the project manager that this is due to a feeling of lack of skills in dealing with new
tasks.
How should the project manager address the issue?
Show answerHide answer
Correct answer: DDiscuss growth and development needs with the team member and provide learning
opportunities accordingly.
Question 12Choose 1
A typically high-performing team member has started to demonstrate a performance drop
as well as some aggressive behaviors toward other team members in meetings.
The project manager has worked with this individual for many months on this project and
has not seen this type of behavior before.
What should the project manager do?
Show answerHide answer
Correct answer: ADiscuss the project manager's observations with the individual to determine why they
are behaving this way.
Question 13Choose 1
A team has individual daily start times for each team member. Sometimes the overlap
between team member working hours is short. During those
times, the interactions and work as a team are reduced and ineffective.
What should the project manager do?
Show answerHide answer
Correct answer: CAsk the team to define a team charter and agree on core working hours.
Question 14Choose 1
During the testing phase of a project, the project manager is made aware that components
delivered from a specific vendor have defects. However, the vendor refuses to fix the
defects because it will incur additional costs for them.
What should the project manager do next?
Show answerHide answer
Correct answer: BReview the acceptance criteria defined with the vendor.
Question 15Choose 3
A project manager is assigned to a time-bound internal project on quality improvement.
During project execution, the project manager observes that a specific team member is
being isolated
by other team members.
Which three actions should the project manager take? (Choose three)
Show answerHide answer
Correct answer: A, C, EArrange and conduct team-building sessions to improve team effectiveness.Get feedback from other team members to understand what led to this situation.Obtain feedback from the isolated team member to understand the situation.
Question 16Choose 1
A project manager just completed a successful deployment and is preparing to transition
the project to an operational state before starting closeout actions. What should the project
manager do to ensure that the project is ready to move to an operational state?
Show answerHide answer
Correct answer: AMeet with the project team to review the work breakdown structure (WBS) and confirm
deliverables have been delivered.
Question 17Choose 1
An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to
the volatility of cryptocurrency, both parties have
agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration
and halt the project when the agreed price is reached.
Which approach should be used in this situation?
Show answerHide answer
Correct answer: DAn incremental approach with a minimum viable product (MVP).
Question 18Choose 1
During daily team standup meetings, team members constantly ask about which tasks they
should focus on first. How should the project
manager ensure the team is fully productive?
Show answerHide answer
Correct answer: DWork with the product owner to ensure the project backlog is prioritized.
Question 19Choose 1
Knowledge sharing has been a key priority for a complex technological project with a large
number of team members. During the project
execution phase, the project manager receives numerous complaints from all team
members that they are overloaded with knowledge-sharing
emails, which contain useful information but are unmanageable due to the high volume.
What should the project manager do to solve this problem?
Show answerHide answer
Correct answer: BEstablish a pull communications method to access knowledge repositories and lessons
learned.
Question 20Choose 1
A company is about to start a complex research project. Due to the level of uncertainty, the
project manager recommends the use of a hybrid approach; however, the organization only
has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
Show answerHide answer
Correct answer: APresent the benefits of a hybrid approach to key stakeholders to get their support.