Question 61 Choose 1
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?
Show answerHide answer

Correct answer: A Provide feedback to the team and conduct a meeting to review the team rules.

Question 62 Choose 1
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?
Show answerHide answer

Correct answer: B Mediator

Question 63 Choose 1
A newly hired team member just joined the project team and reports directly to the project manager. In the first week, this new member tells the project manager that there is a task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?
Show answerHide answer

Correct answer: D Meet the team member and try to plan a course of action together.

Question 64 Choose 1
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?
Show answerHide answer

Correct answer: A Document the lessons learned and implement improvements in the next sprint

Question 65 Choose 1
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?
Show answerHide answer

Correct answer: B Review the stakeholder register to gain insight into the expectations of that team member.

Question 66 Choose 1
A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?
Show answerHide answer

Correct answer: A Evaluate the engagement needs of stakeholders.

Question 67 Choose 1
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?
Show answerHide answer

Correct answer: B Statement of work (SOW)

Question 68 Choose 1
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
Show answerHide answer

Correct answer: D Initiate a review of the procedures with the CTO and the team.

Question 69 Choose 1
A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?
Show answerHide answer

Correct answer: C Identified key stakeholders and included all of them in project agreement discussions.

Question 70 Choose 1
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?
Show answerHide answer

Correct answer: D Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt