A project manager is transferred to another country to perform a project within their
organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
Show answerHide answer
Correct answer: ADetermine a leadership style that is suitable for that location.
Question 22Choose 1
A project is successfully delivering its product outcomes, and the customer satisfaction
rating is high. However, during an internal audit, it is discovered that certain essential
process documents and approvals are missing, and the project is evaluated as being
noncompliant.
What should the project manager do next?
Show answerHide answer
Correct answer: BPerform quality assurance to review the processes against the quality management plan
and identify gaps.
Question 23Choose 1
An intern is replacing a critical resource midway through a sprint To help the intern get up
to speed, the project manager assigns a senior engineer in the team as the intern's mentor
Two months later, the project goes into critical status, delaying the release milestone by a
month.
What should the project manager have done to avoid this scenario?
Show answerHide answer
Correct answer: CAllocated additional time for mentoring
Question 24Choose 1
An organization uses a hybrid approach to project management. A project manager has
been assigned to an external project, project A, where two of the three modules in the
project require machine learning skills. The only machine learning expert in the project
manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
Show answerHide answer
Correct answer: BPlan projectA in sprints, starting with the module that does not require machine learning
skills.
Question 25Choose 2
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations?
(Choose
two)
Show answerHide answer
Correct answer: A, BAsk the agile team to review the updated sprint velocity with the customer.Ask the product owner to review the prioritized backlog with the customer.
Question 26Choose 1
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
Show answerHide answer
Correct answer: DAnalyze the impacts and create a plan for team decision making
Question 27Choose 1
A project manager is in the middle of an agile project comprised of 100 user stories broken
down into five iterations Each user story is worth USS50 The actual expenditure is
US$2,000 and 50 user stories have been delivered.
Which statement is true''
Show answerHide answer
Correct answer: DThe project is under budget and on schedule.
Question 28Choose 1
When reviewing the project team's performance the project manager realizes that the team
velocity is not fast enough to meet the next review gate goal What should the project
manager do?
Show answerHide answer
Correct answer: DUse the standup meeting to assess impediments and problems
Question 29Choose 1
A project manager is attending a progress meeting with a client The client requests a
design change which might potentially add value to the project What action should the
project manager take?
Show answerHide answer
Correct answer: DMake transactional decisions focusing on the project goals
Question 30Choose 1
A project manager for an agile project wants to have a highly engaged team. How should
the project manager achieve this objective?
Show answerHide answer
Correct answer: BPromote an environment where everybody knows what their contribution means to the