Question 11 Choose 1
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
Show answerHide answer

Correct answer: A Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

Question 12 Choose 1
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?
Show answerHide answer

Correct answer: B Speak with the key team member to clarify the situation.

Question 13 Choose 1
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
Show answerHide answer

Correct answer: C Mentor the team member and provide the necessary training.

Question 14 Choose 1
A company is planning a digitization project. Which action should the project manager take first when defining the project scope?
Show answerHide answer

Correct answer: A Assess the current state process to define the scope of the digitization.

Question 15 Choose 1
A junior team member escalates an issue to the project manager about another member's interpersonal skills causing the team to be less effective.

What should the project manager do first?
Show answerHide answer

Correct answer: C Gather information and find the root cause of the problem.

Question 16 Choose 1
A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?
Show answerHide answer

Correct answer: A Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

Question 17 Choose 1
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
Show answerHide answer

Correct answer: C Meet with the project management office (PMO)/compliance entity to work onprocess tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

Question 18 Choose 1
The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project. How should the project manager handle this request?
Show answerHide answer

Correct answer: D Validate if the training is within scope and budget.

Question 19 Choose 1
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?
Show answerHide answer

Correct answer: C Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

Question 20 Choose 1
A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?
Show answerHide answer

Correct answer: D Offer cross-training and mentoring to the new team member

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt