A project manager finds that team members In an agile project are involved in several
different projects due to budget constraints. What should the project manager do?
Show answerHide answer
Correct answer: ARequest the project sponsor prioritize and if necessary, allocate additional budget so the
team can work on a single project
Question 12Choose 1
A key team member shared confidential information about another team member with
management, a practice that is against ethical standards. During a team meeting, some of
the team members requested that the key team member be removed from the team.
What should the project manager do next?
Show answerHide answer
Correct answer: BSpeak with the key team member to clarify the situation.
Question 13Choose 1
A new team member on a self-organizing team is finding it difficult to deliver due to the new
technology being used in the project. What should the project manager do in this situation?
Show answerHide answer
Correct answer: CMentor the team member and provide the necessary training.
Question 14Choose 1
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
Show answerHide answer
Correct answer: AAssess the current state process to define the scope of the digitization.
Question 15Choose 1
A junior team member escalates an issue to the project manager about another
member's interpersonal skills causing the team to be less effective.
What should the project manager do first?
Show answerHide answer
Correct answer: CGather information and find the root cause of the problem.
Question 16Choose 1
A project manager is managing a project aimed at providing incremental deliveries to the
market every three months. The team has been assigned, and the product backlog was
created and prioritized by the product owner. After four iterations, the product owner
escalates complaints to the CEO because the product does not meet the product owner's
expectations.
What should the project manager have done to prevent this situation from happening?
Show answerHide answer
Correct answer: AImplemented sprint reviews with the product owner and retrospectives with the team to
minimize gaps
Question 17Choose 1
A project manager is leading an agile project in an organization that has not executed this
type of project before. In order to ensure the project is following the compliance
requirements, what should the project manager do?
Show answerHide answer
Correct answer: CMeet with the project management office (PMO)/compliance entity to work onprocess
tailoring to ensure that the agile deliverables support the compliance requirements of the
organization.
Question 18Choose 1
The project manager has recently received funding approval for a training program
for the entire project team but has not yet defined the most effective training course. One
team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?
Show answerHide answer
Correct answer: DValidate if the training is within scope and budget.
Question 19Choose 1
A business analyst on the project meets the customer in the elevator and says that due to
constant changes in requirements the development of the product will take more time than
expected What should the project manager do?
Show answerHide answer
Correct answer: CPoint out to the project team and the customer that all information concerning the
timeline of the project should be communicated by the project manager.
Question 20Choose 1
A highly skilled team resource received a job offer and is leaving the project soon What
should the project manager do to maintain project performance while a new team member
is being onboarded?
Show answerHide answer
Correct answer: DOffer cross-training and mentoring to the new team member
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.