Question 51 Choose 1
A project manager is assigned to oversee the deployment of a new product that will be used by the entire organization. A key success factor for the project is the timely and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?
Show answerHide answer

Correct answer: D Engage in creative and iterative negotiations with the leaders of each entity toagree on the launch date.

Question 52 Choose 1
A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?
Show answerHide answer

Correct answer: D Burndown chart

Question 53
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.
Show answerHide answer

Explanation

Question 54 Choose 1
A stakeholder is requesting that the project manager share project status updates on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?
Show answerHide answer

Correct answer: C Review the stakeholder engagement and communications management plans.

Question 55 Choose 1
A project management team received news that a competitor has released the latest version of a program. What should the team do next?
Show answerHide answer

Correct answer: A Review the project plan to evaluate if any updates should be made.

Question 56 Choose 2
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)
Show answerHide answer

Correct answer: C, D Perform a risk identification process with the project team.Consult with the project stakeholders.

Question 57 Choose 1
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
Show answerHide answer

Correct answer: D Validate the proposed change's impact on the project.

Question 58 Choose 1
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?
Show answerHide answer

Correct answer: A Call for a team meeting to identify the root cause for the declining performance

Question 59 Choose 1
An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?
Show answerHide answer

Correct answer: C Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

Question 60 Choose 1
In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the project sponsor that they know very little about the project.

What should the project manager do?
Show answerHide answer

Correct answer: A Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt