A project manager is assigned to oversee the deployment of a new product that
will be used by the entire organization. A key success factor for the project is the timely
and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?
Show answerHide answer
Correct answer: DEngage in creative and iterative negotiations with the leaders of each entity toagree on
the launch date.
Question 52Choose 1
A new agile project manager is trying to determine how the team is performing against the
schedule for a release. Which tool will provide a deeper look into the team's progress?
Show answerHide answer
Correct answer: DBurndown chart
Question 53
A project manager is assigned to a hybrid project involving multiple sectors. The sectors
collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project.
Each sector nominated project representatives, who in turn appointed a product owner who
was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.
Show answerHide answer
Explanation
Question 54Choose 1
A stakeholder is requesting that the project manager share project status updates
on a regular basis. This stakeholder is not included in the regular distribution list.
What should the project manager do?
Show answerHide answer
Correct answer: CReview the stakeholder engagement and communications management plans.
Question 55Choose 1
A project management team received news that a competitor has released the
latest version of a program. What should the team do next?
Show answerHide answer
Correct answer: AReview the project plan to evaluate if any updates should be made.
Question 56Choose 2
A project manager has been assigned to a long-term project. The project manager came
across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
Show answerHide answer
Correct answer: C, DPerform a risk identification process with the project team.Consult with the project stakeholders.
Question 57Choose 1
A project sponsor asks the project team to add an enhancement to the project How should
the project manager address this request?
Show answerHide answer
Correct answer: DValidate the proposed change's impact on the project.
Question 58Choose 1
During the execution phase of a project a new project manager is assigned to replace the
previous project manager As the project manager starts managing the project, they
discover that team performance is significantly decreasing, which is impacting the project's
key performance indicators (KPIs). This team has delivered good performance on similar
projects in the past
What should the project manager do next to improve this situation?
Show answerHide answer
Correct answer: ACall for a team meeting to identify the root cause for the declining performance
Question 59Choose 1
An organization has recently decided to switch from a predictive to an agile delivery
approach. The one ongoing project will still be led by a project manager. The agile teams
for that project have not produced any documentation.
What should the project manager of the ongoing project do?
Show answerHide answer
Correct answer: CCheck with the agile teams to see if the project manager's understanding of the Agile
Manifesto is correct.
Question 60Choose 1
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of
stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
Show answerHide answer
Correct answer: ADiscuss the issue with all stakeholders and work on a communications management