A project manager is hired by a global company. The project manager is an agile specialist
and is tasked with supporting the project team to reduce rework and dissatisfaction.
How should the project manager address these objectives?
Show answerHide answer
Correct answer: CAdopt an incremental cycle of delivering value to the customer.
Question 32Choose 1
local company is developing a new product and. for the first time, using a remote
team for the programming tasks of features. The design for the product comes from the
local team. During the third sprint review, the product owner has concerns about the
project's
outcomes. The remote development team is complaining that they do not clearly
understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
Show answerHide answer
Correct answer: DDetermine the communication needs, environment, and tools to get the message
across.
Question 33Choose 1
A company has agreed to run a transformation project using agile approaches.
During the implementation, there is pushback from the functional groups that the project is
moving too fast.
What should the project manager have done at the beginning of the project to prevent this
from happening?
Show answerHide answer
Correct answer: BAssessed the organizational culture
Question 34
Match the project situation on the left to the meeting on the right where the situation could
occur.
Show answerHide answer
Explanation
Question 35Choose 1
A key agile project team member takes a leave of absence in the middle of an iteration and
will not return to work for a while What should the project manager do next regarding the
feature on which the team member was working?
Show answerHide answer
Correct answer: DReview the work in progress with the product owner to determine the next step
Question 36Choose 1
A project manager has been assigned to take over an existing software project. The project
manager inherited a lean team comprised of key stakeholders, subject matter experts
(SMEs), and senior developers. While reviewing the project status with the team, the
project manager observes that the team seems to lack direction and enthusiasm.
What should the new project manager do?
Show answerHide answer
Correct answer: DEncourage participation in decision making and empower the team.
Question 37Choose 1
An agile team is working on a product deliverable in an organization that is transforming
itself to quickly respond to change. The finance
team is requesting a project budget for the new product.
What should the team do to address this request?
Show answerHide answer
Correct answer: AWork with the finance team to transition to incremental budgeting.
Question 38Choose 1
The project manager of an agile project has been asked to reduce the budget by 30%.
Since this is a small project team, the budget is primarily allocated to resources.
What strategy should the project manager use in order to keep delivering value in a
restricted environment?
Show answerHide answer
Correct answer: APrioritize the product backlog looking for high business value and low effort, and adjust
the project budget and staffing to account for those items.
Question 39Choose 1
A company is transitioning from a predictive to agile delivery of projects. Based on
the requirements, the project team estimates the budget and decides to use a fixed-price
contract with its vendor. However, during the execution of the project, the requirements
evolve and priorities start to change constantly, which puts the project and the estimate at
completion (EAC) off by 40%.
What should the project manager do next?
Show answerHide answer
Correct answer: CMeet with the stakeholders to recommend the use of a time and materials (T&M)
contract to address the problem.
Question 40Choose 1
An organization is transitioning to an agile environment. The project manager finds that
most of the team members are not familiar with an agile environment.
What should the project manager do to address this concern?
Show answerHide answer
Correct answer: DSupport the team members' growth and development.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.