A supplier was supposed to mobilize a government-issued, licensed piece of
equipment two days ago, but did not. The procurement manager was informed that the
supplier failed to check the validity of the license, which expired last week. The supplier
had
already submitted an application to the authorities, but it generally takes one to three
weeks to process the application, which will affect the critical path.
Which action should the project manager take?
Show answerHide answer
Correct answer: CReview the terms of the contract in order to determine next steps.
Question 42Choose 1
At a meeting to receive approval for the project management plan, a project manager
realizes that there is so much detail in the presentation that many of the stakeholders are
not actively engaged in the process. The stakeholders are agreeing to the scope, goals,
and timelines without giving them substantial thought.
How should the project manager proceed?
Show answerHide answer
Correct answer: BSet up information review sessions before reconvening another approval session.
Question 43Choose 1
A project is nearing completion The contingency time has been consumed To ensure that
the final deliverables are achieved fhin budget, the project manager has asked the team to
follow a rigorous process This Is causing some resistance among the team members.
What should the project manager do to address the growing resistance?
Show answerHide answer
Correct answer: CDescribe to the team members how specific tools and techniques can be used to finish
on time
Question 44Choose 1
In an attempt to streamline project communications, a project manager established a
shared portal for all stakeholders to get project information. The sponsor complained about
this system and says that it is ineffective.
What should the project manager have done to prevent this situation from occurring?
Show answerHide answer
Correct answer: AAnalyzed the sponsor's communication requirements.
Question 45Choose 1
A project is behind schedule and over budget, resulting in a problem for the next
deliverable. The project manager informs the stakeholders, who are very concerned about
the project. What should the project manager do to alleviate the stakeholders' concerns?
Show answerHide answer
Correct answer: CSchedule a kick-off session to explain the problems of the project and gain approval and
support
Question 46Choose 1
Experienced team members assigned to a critical project are also supporting several other
projects and this is delaying the critical project. If this critical project is not
delivered, the company could receive a fine from the government. What should the project
manager do?
Show answerHide answer
Correct answer: BReview the resources required for the tasks on the critical path.
Question 47Choose 1
A project manager is managing multiple teams. One team member complains to the project
manager about the favoritism shown by a team lead to another team member and cites
multiple instances.
Risk Response Strategies Analyze if someone else could contribute Record the
observations and move ahead Check for options to exclude the stakeholder
What should the project manager do to resolve the team member's concerns?
Show answerHide answer
Correct answer: BUse a problem-solving approach and set up a discussion with the team lead and team
member.
Question 48Choose 1
An important email from a project sponsor states that a backlog item should be immediately
prioritized. What should the project manager
do with many tasks still open on the Kanban board?
Show answerHide answer
Correct answer: BDiscuss the impact of starting the item with the team.
Question 49Choose 1
A project manager has two projects that are being executed at the same time. The duration
of the critical project must be reduced, but the project manager does not have enough
resources to achieve this goal. In addition, the schedule does not have activities that can
be overlapped.
What should the project manager do?
Show answerHide answer
Correct answer: BAnalyze both projects to determine the most effective use of common resources
Question 50Choose 1
An operations manager continuously raises concerns about a project's benefits to the
company While some concerns are valid most of the time these concerns have caused delays in project meetings
How should the project manager handle this'?
Show answerHide answer
Correct answer: BReview the operations manager's concerns and ensure these concerns are addressed
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.