Question 41 Choose 1
A supplier was supposed to mobilize a government-issued, licensed piece of equipment two days ago, but did not. The procurement manager was informed that the supplier failed to check the validity of the license, which expired last week. The supplier had already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?
Show answerHide answer

Correct answer: C Review the terms of the contract in order to determine next steps.

Question 42 Choose 1
At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?
Show answerHide answer

Correct answer: B Set up information review sessions before reconvening another approval session.

Question 43 Choose 1
A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?
Show answerHide answer

Correct answer: C Describe to the team members how specific tools and techniques can be used to finish on time

Question 44 Choose 1
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?
Show answerHide answer

Correct answer: A Analyzed the sponsor's communication requirements.

Question 45 Choose 1
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
Show answerHide answer

Correct answer: C Schedule a kick-off session to explain the problems of the project and gain approval and support

Question 46 Choose 1
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not delivered, the company could receive a fine from the government. What should the project manager do?
Show answerHide answer

Correct answer: B Review the resources required for the tasks on the critical path.

Question 47 Choose 1
A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?
Show answerHide answer

Correct answer: B Use a problem-solving approach and set up a discussion with the team lead and team member.

Question 48 Choose 1
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager do with many tasks still open on the Kanban board?
Show answerHide answer

Correct answer: B Discuss the impact of starting the item with the team.

Question 49 Choose 1
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?
Show answerHide answer

Correct answer: B Analyze both projects to determine the most effective use of common resources

Question 50 Choose 1
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?
Show answerHide answer

Correct answer: B Review the operations manager's concerns and ensure these concerns are addressed

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt