The client will not agree to closure, claiming that the project team has not performed the
code inspections mandated in the development contract. The project team has performed
the code inspections, however the records are not complete What should the project
manager do?
Show answerHide answer
Correct answer: BHold a meeting with the project team project sponsor and the client to agree to the
further work required to close the project and add to lessons learned
Question 42Choose 1
The project manager is experiencing delays with two critical tasks that are to be executed
by two different teams The project manager realizes that the functional managers of these
two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
Show answerHide answer
Correct answer: AArrange a meeting with the managers and try to reach an agreement.
Question 43Choose 1
The project velocity has recently slipped, and a decision was made to skip testing to
increase the momentum and bong the project back on track What will the project manager
need to focus on as a result of this decision?
Show answerHide answer
Correct answer: CIncreased technical debt
Question 44Choose 1
The project sponsor of a major initiative is consistently changing the prioritization of
modular work packages The team is used to three week sprints and is becoming
increasingly frustrated with the daily changes in scope>
What should the project manager do?
Show answerHide answer
Correct answer: DSet up a meeting with the sponsor to explain the importance of keeping a strict sprint
cycle
Question 45Choose 1
During an iteration of a project, a planned activity becomes more complex. The work
should be delivered in the shortest time possible
What approach should be used in this situation?
Show answerHide answer
Correct answer: DThe cross-functional team member work together to complete the activity
Question 46Choose 1
A project manager is having difficulty acquiring final acceptance of some deliverables from
a stakeholder for reasons that seem to be outside of the project acceptance criteria. What
should the project manager do?
Show answerHide answer
Correct answer: APersuade this stakeholder using emotional intelligence skills to obtain acceptance.
Question 47Choose 2
A large multi-year project requires highly skilled staff for successful deployment The
management team and the project sponsor have analyzed the resource requirements and
agreed to have permanent staff hired for the project to avoid potential budget overrun
However there is a risk of staff turnover during the course of the project, which may have
an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
Show answerHide answer
Correct answer: A, BIntroduce a recognition program to motivate and reward resource performanceEnhance the competencies of the project team through training, mentoring and
coaching.
Question 48Choose 1
During the retrospective ceremony, the agile team is talking about the product owner’s
expectations not being met What should the project manager have done at the beginning of
the project?
Show answerHide answer
Correct answer: CDefined the team ground rules and shared project vision.
Question 49Choose 1
A company has decided to implement a new archiving system A data breach occurred
during the implementation of the project
What should the project manager do first?
Show answerHide answer
Correct answer: AImplement the planned risk response to handle the issue.
Question 50Choose 1
During the review of a project's list of deliverables, one of the stakeholders expressed
concern that one of the requirements will not be addressed. What should the project
manager do?
Show answerHide answer
Correct answer: CReview the requirements traceability matrix with the concerned stakeholder