Question 21 Choose 1
A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?
Show answerHide answer

Correct answer: D Involved stakeholders from all levels of the company so everyone understands the change

Question 22 Choose 1
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
Show answerHide answer

Correct answer: B Evaluate the situation and identify ways to compress the schedule without impacting baselines

Question 23 Choose 1
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
Show answerHide answer

Correct answer: B Evaluate the environmental and regulatory factors and identify high-level risks and assumptions

Question 24 Choose 1
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
Show answerHide answer

Correct answer: D Review the adequacy of the project's governance and ensure that an appropriate structure is in place

Question 25 Choose 1
A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?
Show answerHide answer

Correct answer: C Provide performance feedback as part of the retrospective ceremony.

Question 26 Choose 1
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?
Show answerHide answer

Correct answer: C Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

Question 27 Choose 1
A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?
Show answerHide answer

Correct answer: A Plan to address the issues through backlog grooming and incorporate them into the next sprint

Question 28 Choose 1
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?
Show answerHide answer

Correct answer: C Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

Question 29 Choose 1
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?
Show answerHide answer

Correct answer: D Mentor the new team member on the methodology the project team is using

Question 30 Choose 1
A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?
Show answerHide answer

Correct answer: D Discuss the options with the client as part of the change control process

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt