Question 591 Choose 1
Two project team members are having difficulty communicating updates and issues. One team member prefers telephone calls for any kind of urgency, whereas the other team member prefers email communication. This difference results in a lack of understanding between the team members and sometimes hinders timely communication.

What should the project manager do?
Show answerHide answer

Correct answer: C Ask the team members to follow the ground rules in the project management plan.

Question 592 Choose 1
A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?
Show answerHide answer

Correct answer: D Recommend that the team develop their own guidelines.

Question 593 Choose 1
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?
Show answerHide answer

Correct answer: B Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

Question 594 Choose 1
A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?
Show answerHide answer

Correct answer: B Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

Question 595 Choose 1
A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?
Show answerHide answer

Correct answer: B Schedule a meeting to review the team member's concerns and revisit the decisions if required.

Question 596 Choose 1
A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?
Show answerHide answer

Correct answer: B US$150,000

Question 597 Choose 1
A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?
Show answerHide answer

Correct answer: B Partner with a company that is an expert in this area.

Question 598 Choose 1
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
Show answerHide answer

Correct answer: D Ask the team to work on the unblocked deliverables.

Question 599 Choose 3
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)
Show answerHide answer

Correct answer: B, D, E Ask the testers to provide additional information.Continue with testing according to the plan.Brainstorm the issue with the project team.

Question 600 Choose 1
A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.

What should the project lead do?
Show answerHide answer

Correct answer: B Build a task board on a large wall using sticky notes.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt