An agile project manager would like to convert the requirements document into epics,
capabilities, features and stories In how many iterations should the project manager
estimate the story duration?
Show answerHide answer
Correct answer: BOne iteration
Question 12Choose 1
A geographically distributed project team has development issues between the collocated
and virtual teams causing productivity to decrease. What should the project manager do to
address this issue?
Show answerHide answer
Correct answer: BDevelop protocols for resolving conflicts between team members
Question 13Choose 3
Which three of the following scenarios are impediments to which a scrum master should
pay attention? (Choose three)
Show answerHide answer
Correct answer: A, C, DA team member talking about a user story that is not on the Scrum boardA technology that blocks agile capabilitiesA lack of team empowerment and an inability to self-organize
Question 14Choose 1
After a couple of iterations the project manager decides to present the product to a key
stakeholder The stakeholder's feedback is that the team missed the mark on many features
What should the project manager do to avoid this in the future?
Show answerHide answer
Correct answer: CIncorporate design thinking practices into the project life cycle to better understand the
product's personas and be more effective to match their needs.
Question 15Choose 1
A project manager for a strategic initiative realizes a new stakeholder is interested in the
project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits,
and risks of the project. What should the project manager do to enhance the success of the
project?
Show answerHide answer
Correct answer: CUpdate the stakeholder engagement plan
Question 16
An experienced project manager is overseeing a merger and acquisition project. The
project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
Show answerHide answer
Explanation
Question 17Choose 1
A project manager has just finished initiating a project. While planning the project manager
notes that several essential team members do not have the required skills for key tasks
later in the project.
What should the project manager do first?
Show answerHide answer
Correct answer: ADevelop the resource management plan and ensure adequate training
Question 18Choose 1
The project sponsor on an agile project informed the project lead that an executive would
like an update on the project’s progress What should the project lead do?
Show answerHide answer
Correct answer: BInvite the executive to the project's meeting space to determine if the project information
radiators meet their needs
Question 19Choose 1
During a project’s third iteration, two of the existing team members were replaced As the
project entered the next iteration, the team velocity dropped and the performance started to
slip.
What should the project manager do?
Show answerHide answer
Correct answer: CConvene a team building event to address key performance indicators (KPIs).
Question 20Choose 1
A Scrum team has committed to delivering a specific capability in their first release Multiple
operational issues have prevented the developer from delivering key capabilities. The
technical lead has also given notice that they are resigning from the company
What should the project manager have the Scrum team do to recover from these issues?
Show answerHide answer
Correct answer: AReview constraints in the ongoing sprint planning and evaluate options for the release
plan