Question 11 Choose 1
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?
Show answerHide answer

Correct answer: B One iteration

Question 12 Choose 1
A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?
Show answerHide answer

Correct answer: B Develop protocols for resolving conflicts between team members

Question 13 Choose 3
Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)
Show answerHide answer

Correct answer: A, C, D A team member talking about a user story that is not on the Scrum boardA technology that blocks agile capabilitiesA lack of team empowerment and an inability to self-organize

Question 14 Choose 1
After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?
Show answerHide answer

Correct answer: C Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.

Question 15 Choose 1
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
Show answerHide answer

Correct answer: C Update the stakeholder engagement plan

Question 16
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right
Show answerHide answer

Explanation

Question 17 Choose 1
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?
Show answerHide answer

Correct answer: A Develop the resource management plan and ensure adequate training

Question 18 Choose 1
The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?
Show answerHide answer

Correct answer: B Invite the executive to the project's meeting space to determine if the project information radiators meet their needs

Question 19 Choose 1
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?
Show answerHide answer

Correct answer: C Convene a team building event to address key performance indicators (KPIs).

Question 20 Choose 1
A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?
Show answerHide answer

Correct answer: A Review constraints in the ongoing sprint planning and evaluate options for the release plan

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt