PMI certification · Exam PMP

PMP Mock Exam Page 12

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 6: Exam Pool F, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 6: Exam Pool F questions

111–120 of 143 free
Question 111 Choose 1
A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to enhance the budget estimations for the project?
Show answerHide answer

Correct answer: B Review budget-related lessons learned from similar projects.

Question 112 Choose 1
A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.

What should the project manager do next?
Show answerHide answer

Correct answer: D Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy.

Question 113 Choose 1
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?
Show answerHide answer

Correct answer: C Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

Question 114 Choose 1
A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly to ensure that the stakeholder is up to date on the project. However. the project manager has recently resigned and will not be meeting with the new project manager prior to departure.

How should the project manager ensure that the new project manager continues to update this particular stakeholder?
Show answerHide answer

Correct answer: B Update the stakeholder engagement plan with the specific communication needs for the stakeholder.

Question 115
In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.
Show answerHide answer

Explanation

Question 116 Choose 3
An organization's human resources (HR) department wants to create a high-performing team and implement a project that includes job grading, organizational restructuring, and soft skills training.

To ensure the quality of the project deliverable, which three actions should the project manager take? (Choose 3)
Show answerHide answer

Correct answer: A, C, D Collect feedback and conduct surveys and questionnaires.Document quality gaps and analyze them for continuous improvement.Develop a proper quality management plan with measurable metrics.

Question 117 Choose 1
A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation.

What should the project manager do next?
Show answerHide answer

Correct answer: A Meet with the team member to understand their concerns and/or issues.

Question 118 Choose 1
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?
Show answerHide answer

Correct answer: C Conducted periodic reviews with the manager on resource availability.

Question 119 Choose 1
Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?
Show answerHide answer

Correct answer: A Assess and prioritize the impact of the new law on the project plan.

Question 120 Choose 1
During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?
Show answerHide answer

Correct answer: C Stakeholder engagement assessment matrix

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt