A project manager who recently joined the company has been assigned to manage a
software project for a major recurring customer. What should the project manager do to
enhance the budget estimations for the project?
Show answerHide answer
Correct answer: BReview budget-related lessons learned from similar projects.
Question 112Choose 1
A project manager has been assigned to a project after the charter has been approved.
While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?
Show answerHide answer
Correct answer: DImmediately discuss this with the project sponsor and request to revisit the budget to
ensure its accuracy.
Question 113Choose 1
A team member has experienced personal conflicts on past projects, making them nervous
about working on the current project. The project
manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
Show answerHide answer
Correct answer: CAdvise the team member to focus on the current project and consider the past conflicts
as lessons learned.
Question 114Choose 1
A primary stakeholder is unable to join the project status meetings consistently. The project
manager has been communicating with this stakeholder informally and regularly
to ensure that the stakeholder is up to date on the project. However. the project manager
has recently resigned and will not be meeting with the new project manager prior to departure.
How should the project manager ensure that the new project manager continues to update
this particular stakeholder?
Show answerHide answer
Correct answer: BUpdate the stakeholder engagement plan with the specific communication needs for the
stakeholder.
Question 115
In an effort to modernize the technology for a project, the project manager has been
discussing risk prioritization with the project team. The project manager determines that
additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
Show answerHide answer
Explanation
Question 116Choose 3
An organization's human resources (HR) department wants to create a high-performing
team and implement a project that includes job grading, organizational restructuring, and
soft skills training.
To ensure the quality of the project deliverable, which three actions should the project
manager take? (Choose 3)
Show answerHide answer
Correct answer: A, C, DCollect feedback and conduct surveys and questionnaires.Document quality gaps and analyze them for continuous improvement.Develop a proper quality management plan with measurable metrics.
Question 117Choose 1
A project manager is managing a mobile application development project when one of the
experienced team members starts missing deadlines. The delays will impact project implementation.
What should the project manager do next?
Show answerHide answer
Correct answer: AMeet with the team member to understand their concerns and/or issues.
Question 118Choose 1
A project is behind schedule because of a delayed equipment installation. This is affecting
many other activities. The manager responsible for the
equipment delivery notified the project manager that there is a capacity issue for the team
doing the installation.
What should the project manager have done to prevent this situation from happening?
Show answerHide answer
Correct answer: CConducted periodic reviews with the manager on resource availability.
Question 119Choose 1
Anew law was published about zoning permits for telecom towers. This may cause cost
and schedule overruns for the new network rollout.
What should the project manager do?
Show answerHide answer
Correct answer: AAssess and prioritize the impact of the new law on the project plan.
Question 120Choose 1
During a regular project progress meeting, the CEO informed the project manager that a
major stakeholder has been unaware of recent developments on the project. The
project manager is sure that the stakeholder was duly identified and classified in the
stakeholder register.
Which project document should the project manager review in order to determine the
reason for this issue?