A project team is transitioning to agile. During the sprint retrospective, a new member of
the team proposed a more structured approach for capturing requirements that would
improve clarity and reduce rework. Although the team members are happy to use it,
changing the way business requirements are described requires agreement from an
influential business manager.
What should the project manager do?
Show answerHide answer
Correct answer: AContact the business manager and discuss the benefits of the new approach.
Question 132Choose 1
A human resource (HR) acquisition process for a large project has recently changed. One
major process change includes the approval of the financial manager and the recruitment
manager. This change to the process implies longer processing. The project urgently
needs new resources.
What should the project manager do?
Show answerHide answer
Correct answer: BAssess the impact of the change and review the project management plan for next
steps.
Question 133Choose 2
A project manager is reviewing several potential changes to the contract with third-party
vendors.
Which two changes could trigger a modification to the vendor contractual obligations?
(Choose 2)
Show answerHide answer
Correct answer: C, EIntroducing additional requirements based on new regulationsReplacing a material type based on product availability
Question 134Choose 1
A multicultural team is working on a project. After a few months of observation, the project
manager realizes that two team members are not responding to the construction manager
properly. The project manager spoke to the team members individually and found that both
had cultural differences with the construction manager.
What should the project manager do to improve the situation?
Show answerHide answer
Correct answer: DDiscuss the team members' concern with the construction manager and seek solutions.
Question 135Choose 1
A project manager is developing the stakeholder register and is having trouble
understanding the motivation of some of the stakeholders. What should the project
manager
do to get this information?
Show answerHide answer
Correct answer: AOrganize a one-on-one conversation with each stakeholder.
Question 136Choose 1
A project sponsor would like to include a new deliverable. The sponsor contacts the project
manager in order to seek advice on the most efficient approach to complete the deliverable
within the next 2 months.
What should the project manager do?
Show answerHide answer
Correct answer: CSuggest that the sponsor conduct a cost-benefit analysis to determine feasibility.
Question 137Choose 1
A new project needs to be submitted for urgent funding approval. The project, which will
use a new technology, is vital to the organization. The entire Scrum team has worked
together for over 3 years on multiple projects and delivered the previous project under the
approved budget.
Which estimation technique should the project manager implement in this context?
Show answerHide answer
Correct answer: CStory points
Question 138Choose 1
An agile team is working on a 2-week sprint to deliver business value. About 1 week after
the sprint starts, the team members do not feel
confident about the product increment they are building. They do not want to wait until the
end of the sprint and want to validate the product
increment with the product owner now.
What should the project manager do to mitigate this risk?
Show answerHide answer
Correct answer: BSchedule an additional interim demo with the product owner.
Question 139Choose 1
A project team created user stories after understanding the customer requirements. As the
project progresses, the project manager observes that
there are too many change requests. The team feels that the outcomes they are working
on are not aligned with the customer requirements.
What should the project manager do?
Show answerHide answer
Correct answer: BArrange for a workshop with the customer to understand the business values expected
from the outcomes.
Question 140Choose 1
At a project meeting, a business analyst requires input from a marketing consultant to
continue working on a task. The business analyst has tried
to contact the consultant but has been told that the consultant does not have the time to
discuss the project.
What should the project manager do to move the project forward?
Show answerHide answer
Correct answer: CDiscuss the request with the consultant and set up time with the business analyst and
consultant to discuss the project requirements.