A company is implementing a project with team members located in different countries and
time zones. Individual performance is satisfactory, but the team's performance as
a whole is low, especially in terms of group activities.
What should the project manager do?
Show answerHide answer
Correct answer: DFacilitate communication and team building.
Question 122Choose 3
A company hired a new project lead to incorporate some agile practices.
Which three changes should the project lead incorporate in the existing team meetings?
(Choose 3)
Show answerHide answer
Correct answer: A, B, EAdd sprints and sprint reviews as necessary.Agree with the team on some ground rules.Encourage everyone to participate in the daily meetings.
Question 123Choose 1
A project team member is sick and will not be able to return to the project for a few weeks.
During the daily meeting, the team shares their concerns as the sick team member was the
only one skilled in the component they were developing.
What should the project manager have done to prevent this?
Show answerHide answer
Correct answer: DFacilitated cross-functional knowledge transfer during the project.
Question 124Choose 1
A project manager is working on a software development project for an oil and gas client
using an agile approach. The project manager is having difficulty preparing the schedule
because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?v
Show answerHide answer
Correct answer: AIterative scheduling
Question 125Choose 1
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased
equipment will be delayed. The project manager is concerned that this will directly effect
the project schedule.
What should the project manager do next?
Show answerHide answer
Correct answer: BUpdate the risk register and discuss it with the project stakeholders.
Question 126Choose 1
An agile team has been assigned to a project that mandates the implementation of
changes to key government products. The team has been given 6 months to fulfill this
mandate.
What should the team lead do next?
Show answerHide answer
Correct answer: BCreate the epics at a high level for the requirements and begin grooming sessions.
Question 127Choose 1
The scope of a project is to replace the street signs within a 10-km radius. The client does
not want to sign the project closure report if the radius
is not extended by 1 km, to be aligned with the council's development plan.
What should the project manager do?
Show answerHide answer
Correct answer: DObtain formal acceptance for the completed work and submit a change request.
Question 128Choose 1
A project lead is working on an agile project to build the team's vision, including the
decision-making process. It was decided that the team will
vote on items, and if 90% of the team agrees on a decision, then it will be carried forward.
At the very first technical design meeting, the team
makes a decision that the project lead strongly disagrees with.
How should the project lead proceed?
Show answerHide answer
Correct answer: CNote the reasons for the disagreement and let the team proceed.
Question 129Choose 1
A project manager is newly appointed to lead a project team that will be working remotely.
The project manager decided to use a set of tools that
worked well for previous projects. However, a few team members are not happy with this
plan.
What should the project manager have done to avoid this?
Show answerHide answer
Correct answer: BMet with the project team to determine their collaboration needs and identified tools that
will work best.
Question 130Choose 1
A project manager is leading a project that is in the execution phase. Due to a company
reorganization, some key project team members are likely to leave the project.
What should the project manager do next?
Show answerHide answer
Correct answer: DDetermine the impact to the project and implement mitigations per the project
management plan.