Question 121 Choose 1
A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.

What should the project manager do?
Show answerHide answer

Correct answer: D Facilitate communication and team building.

Question 122 Choose 3
A company hired a new project lead to incorporate some agile practices.

Which three changes should the project lead incorporate in the existing team meetings?
(Choose 3)
Show answerHide answer

Correct answer: A, B, E Add sprints and sprint reviews as necessary.Agree with the team on some ground rules.Encourage everyone to participate in the daily meetings.

Question 123 Choose 1
A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?
Show answerHide answer

Correct answer: D Facilitated cross-functional knowledge transfer during the project.

Question 124 Choose 1
A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?v
Show answerHide answer

Correct answer: A Iterative scheduling

Question 125 Choose 1
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.

What should the project manager do next?
Show answerHide answer

Correct answer: B Update the risk register and discuss it with the project stakeholders.

Question 126 Choose 1
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.

What should the team lead do next?
Show answerHide answer

Correct answer: B Create the epics at a high level for the requirements and begin grooming sessions.

Question 127 Choose 1
The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius is not extended by 1 km, to be aligned with the council's development plan.

What should the project manager do?
Show answerHide answer

Correct answer: D Obtain formal acceptance for the completed work and submit a change request.

Question 128 Choose 1
A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?
Show answerHide answer

Correct answer: C Note the reasons for the disagreement and let the team proceed.

Question 129 Choose 1
A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that worked well for previous projects. However, a few team members are not happy with this plan.

What should the project manager have done to avoid this?
Show answerHide answer

Correct answer: B Met with the project team to determine their collaboration needs and identified tools that will work best.

Question 130 Choose 1
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?
Show answerHide answer

Correct answer: D Determine the impact to the project and implement mitigations per the project management plan.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt