Question 71 Choose 1
A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?
Show answerHide answer

Correct answer: D Meet with subject matter experts (SMEs) to assess the impact to objectives

Question 72 Choose 1
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?
Show answerHide answer

Correct answer: C The project manager should allow the resources to periodically choose on which team they would like to work.

Question 73 Choose 1
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?
Show answerHide answer

Correct answer: D The team with the least amount of defects in their deliverables

Question 74 Choose 1
During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
Show answerHide answer

Correct answer: B Validate acceptance criteria with stakeholders prior to backlog refinement

Question 75 Choose 1
A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?
Show answerHide answer

Correct answer: C Adopt an iterative rollout approach that delivers the highest business value earlier

Question 76 Choose 1
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
Show answerHide answer

Correct answer: B Identify the goal of each work product

Question 77 Choose 1
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?
Show answerHide answer

Correct answer: A Execute it as a Scrum project

Question 78 Choose 1
The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?
Show answerHide answer

Correct answer: B Perform a stakeholder evaluation

Question 79 Choose 1
A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project

What should the project manager do?
Show answerHide answer

Correct answer: D Implement a reward system aimed to keep the team engaged and motivated

Question 80 Choose 1
A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?
Show answerHide answer

Correct answer: C Give the team autonomy to make their own decisions on how to perform the tasks.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt