A project to develop a large hydropower plant is in the implementation phase and is
managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?
Show answerHide answer
Correct answer: CContinually survey the quality of the deliverable
Question 52Choose 2
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives
feedback from the stakeholders that could result in a change in the product What two
actions should the project manager take? (Choose two)
Show answerHide answer
Correct answer: A, BAsk the stakeholders about the priority of this changeAsk the product owner to review the product backlog
Question 53Choose 1
During the execution of a project, the finance team identified that they were not involved in
building the business case for the project and will not approve the estimated return on
investment (ROI). What should the project manager do?
Show answerHide answer
Correct answer: CSchedule a meeting with the product owner and finance team to agree on course
corrections
Question 54Choose 1
A project manager is managing a project to develop a new tool Because of the nature of
the project, the project manager decides to use an agile approach One of the identified
risks becomes an issue when the project manager finds out that another company patented
a very similar tool.
What should the project manager do to address this issued
Show answerHide answer
Correct answer: ASchedule a meeting with critical stakeholders to review the issue and decide on the next
steps
Question 55Choose 1
During project execution, the project manager notices that the work performance reports
have deteriorated drastically in less than two weeks The project team in country A is
complaining about delays resulting from holidays occurring in country B that have impacted
their project team
How should the project manager handle this situation?
Show answerHide answer
Correct answer: DReview the risk management plan to evaluate the probability and impact of these delays
Question 56Choose 1
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and
responsibilities for the project What should the project manager do in this situation?
Show answerHide answer
Correct answer: DAsk the functional manager to create a specific responsible, accountable, consult, and
inform (RACI) chart for the team member
Question 57Choose 1
A project manager is leading a project which shows a trend to exceed the cost baseline
What should the project manager do first to manage the budget?
Show answerHide answer
Correct answer: BMeet with the project team to analyze the actual cost to determine deviations
Question 58Choose 1
The tables show the requirements for an agile project with the anticipated return on
investment (ROI) and identified project risks, along with the analysis details .
What should be the priority order in the product backlog?
A new team member is added to a self-organizing team. The new team member is
reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
Show answerHide answer
Correct answer: A, CRevisit the team's discussion on team behaviors and normsCoach the new team member to improve engagement with the team.
Question 60Choose 1
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How
should the servant leader apply emotional intelligence to leverage this situation to benefit
the project?
Show answerHide answer
Correct answer: DAsk the team member to use their recently acquired knowledge to develop and provide
training to the team