During project execution, the risk owner is monitoring the critical speed rate of a power
engine to eventually trigger the defined risk-response strategy. During the risk assessment
and management process phase, it was defined that the power engine has the following
characteristics
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1.500 rpm (rate-per-minute) -> warns of max rate allowed
1.400pm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
Show answerHide answer
Correct answer: C1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that
triggers a response strategy
Question 62Choose 1
A project manager is managing a complex research project with a high level of uncertainty
A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
Show answerHide answer
Correct answer: CPaired work and the customer role method.
Question 63Choose 1
A company that is heavily focused on delivering projects using predictive approaches on-
boards a new project manager who uses hybrid approaches The scope of the project
contains a number of unclear requirements.
How should the project manager plan the delivery of the project?
Show answerHide answer
Correct answer: DBreak down the requirements and prioritize the requirements into iterative work
packages
Question 64Choose 1
The customer is reviewing the new reporting system and informs the project manager that
one of the components in the printing module is not complete The project manager reviews
the work breakdown structure (WBS) and confirms that the component Is included.
What does the project manager need to do first?
Show answerHide answer
Correct answer: DMeet with the project team to understand the issue and define actions.
Question 65Choose 3
A project manager has been assigned to an education project with the objective of training
a workforce in application development One of the deliverables is to provide internships to
the best students in the customer's active projects However the customer does not have
enough projects in progress right now The project manager decides to create several
internal projects in order to ensure the internships
Which three actions should the project manager take to fulfill this scenario without adding
costs for the customer? (Choose three)
Show answerHide answer
Correct answer: B, D, ECreate a change request with the scope of the new internal projects.Create a work breakdown structure (WBS) of the new scope with the internal projectsManage the quality of the delivery
Question 66Choose 1
Two weeks after the approval of the project management plan for a global project, the
project manager noticed that it was approved based on a different level of understanding
by international stakeholders and is not what the project manager presented for approval
What should the project manager have done to prevent this from happening?
Show answerHide answer
Correct answer: DValidated each stakeholder's understanding during the kick-off meeting
Question 67Choose 1
A project team is having difficulties understanding technical details regarding requirements
The information was not initially provided by the customer, but the information is critical in
the current iteration for clarification on how tasks need to be accomplished
How should the project manager approach this situation?
Show answerHide answer
Correct answer: ARequest that the customer reviews and clarifies feature definitions for the current sprint
Question 68Choose 1
An agile project is running activities to define the minimum viable product (MVP) During the
session, the project manager identifies some mandatory regulations but there is no
consensus to include these regulations in the MVP because it may extend the duration of
the project
What should the project manager do?
Show answerHide answer
Correct answer: BGet commitment from the team to include all of the required regulations
Question 69Choose 1
The product team is progressing with a prototyping approach to deliver a multiyear
business initiative A few user stones are taking longer to be delivered.
What should the project manager do?
Show answerHide answer
Correct answer: CDetermine cross-dependencies and plan a spike in the next spont
Question 70Choose 1
A project manager has been appointed to a multimillion-dollar project The project is
considered to be high risk since no similar projects have been undertaken before and there
is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
Show answerHide answer
Correct answer: BEstablish dialogue with stakeholders on the project constraints, assumptions, and critical
inputs