After gathering all the requirements for a project with dependencies on external
stakeholders, the project team is finishing the second iteration At this point, the project
manager learns about a possible change in regulations that would prevent the product
launch
What should the project manager do to realize benefits?
Show answerHide answer
Correct answer: CReview target benefits.
Question 32Choose 1
A key project stakeholder showed interest in the beginning of a complex agile project but
has become less involved as the sprint has progressed due to additional responsibilities A
few sprints later, the key stakeholder rejected a feature deliverable The team is reworking
the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
Show answerHide answer
Correct answer: BCustomized stakeholder communications based on the stakeholders’ needs
Question 33Choose 2
After completion of a project with specific users in various countries, the project manager's
supervisor asks if the project users are satisfied with the way the project was run. What two
actions should the project manager take? (Choose two)
Show answerHide answer
Correct answer: C, ESend a questionnaire to the project participants and seek their feedback.Deliver the project materials to the users and see if they have any comments
Question 34Choose 1
During the development of a product, the project manager observes conflicts between
project stakeholders, resulting in deliverable and output approval delays On which area
should the project manager focus?
Show answerHide answer
Correct answer: CRevisiting the stakeholder engagement plan, focusing on specific overlooked
stakeholders
Question 35Choose 1
A new project manager is planning an information security project for a company that
resides in different countries. What is the first step the project manager should take to
gather customer requirements?
Show answerHide answer
Correct answer: DConduct project planning meetings in one location with relevant stakeholders
Question 36
A project manager is worried that a key stakeholder is not participating in the project and
has concluded that the final product is not as good as it could have been if the stakeholder
had been more involved Drag the scenario on the left to the correct risk response strategy
on the right
Show answerHide answer
Explanation
Question 37Choose 1
During a daily standup meeting, a roadblock was raised that is preventing one of the team
members from proceeding with work The project manager figures out that it is due to a
technical issue.
What should the project manager do to prioritize this critical impediment?
Show answerHide answer
Correct answer: BPerform a brainstorming session to address the issue and add the solution to the sprint.
Question 38Choose 1
A transportation company is transforming its operational processes and the mam system
this company uses to move freight The scope statement is in place An iterative delivery
approach has been agreed by all stakeholders. What does the project manager need to do
next to help the team understand the work that needs to be done?
Show answerHide answer
Correct answer: AWork with the team to decompose the scope into a WBS and work packages in order to
create required deliverables and timelines.
Question 39Choose 1
During the course of a project, the team develops negative group behaviors and becomes
unmotivated and unproductive. What should the project manager do to improve the project
team's performance?
Show answerHide answer
Correct answer: DConduct a root cause analysis session
Question 40Choose 1
A project manager is tracking a project, but a key stakeholder will not accept the project's
key performance indicator (KPI) results Which tool or technique should the project manager
use?
Show answerHide answer
Correct answer: CContext diagram