Question 41 Choose 1
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
Show answerHide answer

Correct answer: B Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned

Question 42 Choose 1
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?
Show answerHide answer

Correct answer: A Arrange a meeting with the managers and try to reach an agreement.

Question 43 Choose 1
The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
Show answerHide answer

Correct answer: C Increased technical debt

Question 44 Choose 1
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?
Show answerHide answer

Correct answer: D Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Question 45 Choose 1
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?
Show answerHide answer

Correct answer: D The cross-functional team member work together to complete the activity

Question 46 Choose 1
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
Show answerHide answer

Correct answer: A Persuade this stakeholder using emotional intelligence skills to obtain acceptance.

Question 47 Choose 2
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)
Show answerHide answer

Correct answer: A, B Introduce a recognition program to motivate and reward resource performanceEnhance the competencies of the project team through training, mentoring and coaching.

Question 48 Choose 1
During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?
Show answerHide answer

Correct answer: C Defined the team ground rules and shared project vision.

Question 49 Choose 1
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?
Show answerHide answer

Correct answer: A Implement the planned risk response to handle the issue.

Question 50 Choose 1
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
Show answerHide answer

Correct answer: C Review the requirements traceability matrix with the concerned stakeholder

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt