Before kicking off a high-priority and complex project, what should the project manager do
to ensure all project stakeholders are aware of their role scope as it relates to project
activities?
Show answerHide answer
Correct answer: BCreate a responsible, accountable, consulted, informed (RACI) chart.
Question 602Choose 1
A project manager is in the process of authoring the communications management plan for
a new project. One of the project's stakeholders has a habit of posting work updates on
social media, which may include confidential project status updates.
What should the project manager do?
Show answerHide answer
Correct answer: BEnsure that sensitive information is not included in stakeholder updates.
Question 603Choose 1
A project is late due to a large number of scope changes. This was raised as a risk in the
risk register during the initiation phase. The team is afraid that they will be blamed in case
of failure and recommends that the project manager ask for an extension.
What should the project manager do first?
Show answerHide answer
Correct answer: CRefer to the risk register and follow the mitigation plan.
Question 604Choose 1
A project manager is leading a project with a team that is comprised of both experienced
and inexperienced team members. What should the project manager do to ensure an
effective project team?
Show answerHide answer
Correct answer: CIdentify how the team members with no experience can contribute according to their
capabilities and provide training if needed.
Question 605Choose 1
An agile team is struggling to successfully deliver what they have committed. During the
daily status meetings, the project manager notices that the most senior engineer is doing
all of the talking, leaving little time for the other members to share their status. The team's
performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
Show answerHide answer
Correct answer: CCoach the team to be more inclusive.
Question 606Choose 1
A project manager assigned to an agile project realizes that after iteration demos, new user
stories to fix issues reported by the product owner are not included in prioritization of the
following sprint. This has led to a high number of unprioritized stories in the backlog and
will lead to delay of the product release.
What should the project manager do?
Show answerHide answer
Correct answer: BAsk the team and product owner to reprioritize the user stories in the backlog for an
updated iteration schedule.
Question 607Choose 1
A work package to configure new computer hardware is received, and a list of related
project activities have also been identified. What should the project manager do?
Show answerHide answer
Correct answer: BEstimate the resources needed for the activities.
Question 608Choose 1
A functional team member often becomes disruptive during status meetings and attempts
to derail progress with the key stakeholders. This team member often discusses why the
project will not be successful.
What should the project manager do?
Show answerHide answer
Correct answer: CIdentify the root cause of the team member's misunderstanding.
A complex project is being developed in phases as per the original plan. Half of the
systems have been handed over to the customer for operational use. There is no delay in
the schedule. However, the customer is still not happy because some of the systems
handed over are no longer useful due to changes in the environment. What should the
project manager have done to avoid this?
Show answerHide answer
Correct answer: CReviewed benefits realization with the customer regularly and constantly aligned
expectations
Question 610Choose 1
After a project review meeting, a key stakeholder tells another stakeholder they do not trust
the project status report. The second stakeholder approaches the project manager and
mentions the conversation. What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a meeting with the key stakeholder to address the issue and obtain direct
feedback