Question 621 Choose 1
A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when project deliverables are considered complete. How should the project manager respond?
Show answerHide answer

Correct answer: D Items are considered complete when they satisfy the definition of done (DoD)

Question 622 Choose 1
A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?
Show answerHide answer

Correct answer: B Conduct simulations to determine the best way forward to ensure timely delivery

Question 623 Choose 1
Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?
Show answerHide answer

Correct answer: D Review the project schedule and find ways to fast-track the overall project schedule.

Question 624 Choose 1
A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?
Show answerHide answer

Correct answer: C Analyze this stakeholder’s interest and impact.

Question 625 Choose 1
A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?
Show answerHide answer

Correct answer: B An increase in the project risk

Question 626 Choose 1
A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?
Show answerHide answer

Correct answer: C Perform an analysis to better understand the communication needs and preferences of each group

Question 627 Choose 1
During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?
Show answerHide answer

Correct answer: C Arrange a meeting with the two departments to understand their differences and address their needs

Question 628 Choose 1
A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?
Show answerHide answer

Correct answer: C Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.

Question 629 Choose 1
An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?
Show answerHide answer

Correct answer: A Review the evidence of the quality assurance (QA) activities performed.

Question 630 Choose 1
A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?
Show answerHide answer

Correct answer: D Develop a communications management plan to share updates with stakeholders

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt