A project manager is working on an agile project. The organization does not have
experience with agile delivery. During business case development, the new product owner
asks when project deliverables are considered complete. How should the project manager
respond?
Show answerHide answer
Correct answer: DItems are considered complete when they satisfy the definition of done (DoD)
Question 622Choose 1
A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline.
The sponsor asks the project manager to check whether the project team can do anything
to deliver on time. What should the project manager do first?
Show answerHide answer
Correct answer: BConduct simulations to determine the best way forward to ensure timely delivery
Question 623Choose 1
Three months after creating a project schedule, the scope of a project significantly
changed, resulting in a schedule rebaselining. One month after rebaselining, the project is
two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the
project manager do to help get the project back on schedule?
Show answerHide answer
Correct answer: DReview the project schedule and find ways to fast-track the overall project schedule.
Question 624Choose 1
A new stakeholder is unaware of the existence of the project a few weeks before the final
deliverable and project completion. What should the project manager do first?
Show answerHide answer
Correct answer: CAnalyze this stakeholder’s interest and impact.
Question 625Choose 1
A project has a schedule performance index (SPI) of 0.75 and a cost performance index
(CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing
the project schedule to bring the project back on track again. What could be a secondary
result of these actions?
Show answerHide answer
Correct answer: BAn increase in the project risk
Question 626Choose 1
A project manager is leading a complex project with stakeholders from different countries,
cultures, and languages. What can the project manager do to manage this diverse group of
stakeholders?
Show answerHide answer
Correct answer: CPerform an analysis to better understand the communication needs and preferences of
each group
Question 627Choose 1
During a blueprint review meeting, the finance department representative is not
comfortable with a proposed solution that favors another department. As a result,
document approval is delayed and impacts the project schedule. What should the project
manager do?
Show answerHide answer
Correct answer: CArrange a meeting with the two departments to understand their differences and
address their needs
Question 628Choose 1
A project manager is working on a large event and developing budgets for sign-off. The
stakeholders and project sponsor are all working remotely using various tools to ensure
that all documentation is tracked and handled discretely and appropriately. The primary
stakeholder has missed several deadlines for the milestone sign-offs, resulting in the
project manager being forced to find alternative suppliers for items, now at higher costs.
When questioned regarding the delays, the stakeholder says the notifications hadn’t
appeared in their email inbox. How should the project manager proceed?
Show answerHide answer
Correct answer: CAssess whether the communications channels are appropriate for the primary
stakeholder and amend accordingly.
Question 629Choose 1
An increment was delivered to the customer at the end of a sprint. The customer complains
that the product does not meet the expected quality and will require some rework. What
should the project manager do next?
Show answerHide answer
Correct answer: AReview the evidence of the quality assurance (QA) activities performed.
Question 630Choose 1
A project manager has just started a new project for an organization that dislikes budget
and schedule deviations. The project stakeholders are very engaged and want to ensure
there is clear visibility of the project’s risks and progress. How should the project manager
handle stakeholder expectations?
Show answerHide answer
Correct answer: DDevelop a communications management plan to share updates with stakeholders
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.