Question 71 Choose 1

It is now late October and the project is in stage 3. The label design competition has been
held and the photos of the staff have been taken. The CEO and Marketing Director still
need to choose the winning label design and the 12 photos for the calendar. However, the
Executive has learned that two competitors are issuing calendars to MNO's customers by
the middle of November. After analyzing the impact of this Issue, one of the options the
Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if
the project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for
the company?

Show answerHide answer

Correct answer: D

End Project Report

Question 72 Choose 1

The project is part of a program to develop more training courses that respond to new legislation. The project
manager has requested that project support be made available from the program. As a result, the executive has
confirmed that this will be carried out by the program office.
Is this appropriate, and why?

Show answerHide answer

Correct answer: A

Yes, because the program office should provide support to projects, if requested.

Question 73 Choose 1

Project Scenario – Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials
and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to
health and safety on construction sites. The project will deliver “capability to provide health and safety
training”, including the materials needed for classroom-based training and e-learning. The expected benefits
for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for
classroom-based training will be delivered by ABC Company’s development team. All course materials will
be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the
course materials to other training companies as part of their operational business. ABC Company will use their
own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The
course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC
Company has grown quickly into a successful training company. It delivers a range of accredited professional
training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets
for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring
supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development
budget. His department organizes courses, venues and trainers. They work with the Product and the Sales
teams to provide a comprehensive training schedule. ABC Company’s IT manager reports to the Operations
Director.
The Business Development Director has recently been appointed to identify new training needs and propose
new products. She will work with the Operations. Director to ensure a cost-conscious approach and that
appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for
developing training materials and gaining accreditation, in accordance with the standard course development
model. Course developers in his team have skills in a range of development technologies and are allocated to
projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that
internal and external trainers deliver ABC Company training courses to the required standard. He also checks
course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and
configuration management. He recently led a project to consolidate all company quality systems into one
quality management system and set up a corporate quality department, now managed by the Corporate Quality
Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the
company’s document management system and now operates it across the business. She manages a team of
administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new
markets for the courses and material. All account managers and the marketing team report to him. They
promote existing training courses to other training companies and existing customers.
End of the additional information.
During stage 3, a work package was assigned to produce the 'planned pilot courses'. The product's quality
criteria were defined and baselined before the work package was agreed.
Which principle is being applied, and why?

Show answerHide answer

Correct answer: B

'Focus on products', because a product should be agreed and defined to a reasonable extent before
production begins.

Question 74 Choose 1

The project is part of a program to increase the number of ABC courses that respond to legislation. The
program manager has instructed the project manager to deliver the 'e-learning course' incrementally. The
project manager has asked the program manager how often the highlight reports are required, and what format
the reports should be presented in.
Is this an appropriate approach to controlling progress, and why?

Show answerHide answer

Correct answer: D

No, because the progress controls should be documented in the project initiation documentation

Question 75 Choose 1

MANAGING PRODUCT DELIVERY
Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to
develop the 'classroom-based training material' discovered that the representatives assigned to check the
products were unsuitable.
Which action should the team manager take in response?

 

Show answerHide answer

Correct answer: B

Advise the project manager of this risk.

Question 76 Choose 1

The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage
is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that
the 'training venue specifications' will be delivered in stage 3 instead of stage 2.
Is this an appropriate action, and why?

Show answerHide answer

Correct answer: D

No, because the stage deviation should be referred to the project board for a decision.

Question 77 Choose 1

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before
accepting the work package, the team manager produces the team plan and finds that the expected delivery
date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package,
within the current stage tolerance. The work package is then accepted by the team manager.
Is this an appropriate application of the 'manage product delivery' process, and why?

Show answerHide answer

Correct answer: B

Yes, because the team manager should agree the limits within which the work is to be completed.

That's the last free question

You've seen the free 30% (77 of 274 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt