Question 61 Choose 1

Which statement is an appropriate entry for the project approach heading within the Project
Brief?

Show answerHide answer

Correct answer: C

The Information Technology Division and the Facilities Division will be outsourced to a
single service provider.

Question 62 Choose 1

Which statement is an appropriate entry for the Initiation Stage Plan?

Show answerHide answer

Correct answer: B

The plan is based on the external outsourcing consultants being available at the start of
the initiation stage.

Question 63 Choose 1

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues, lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reports
to the Project Board.
Without a Risk Register how can project risks, the progress of risk actions taken to date
and the current status of residual risks be measured?

Show answerHide answer

Correct answer: A

The Daily Log was correctly used to monitor risks during the Starting up a Project
process. It will be used to capture all risks, actions, decisions, assumptions

Question 64 Choose 1

While capturing previous lessons, the Project Manager discovered several interesting facts
about outsourcing.
Which fact is an appropriate lesson for the Outsourcing project?

Show answerHide answer

Correct answer: C

Contracts with service providers should include the timescale within which readiness for
service is expected following the transfer of equipment and staff.

Question 65 Choose 1

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues. lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reportsto the Project Board.
There is no Project Brief. How can there be a common understanding of the desired
outcomes for the prepared calendar pack?

Show answerHide answer

Correct answer: C

The simple Project Initiation Documentation contains the project definition.

Question 66 Choose 1

Which of the following is NOT a trigger for the project manager to authorize a work
package?

Show answerHide answer

Correct answer: D

Reporting highlights

Question 67 Choose 2

Two weeks after starting work the Team Manager noticed that each completed product had
exceeded its estimated effort by around 10%. If this trend continues the Work Package will
exceed its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?

Show answerHide answer

Correct answer: A, E

Update the Team Plan by increasing all future work estimates by 10%.

Raise an issue that costs will exceed tolerance if the current trend continues

Question 68 Choose 2

The Work Package has been in progress for four weeks and has four weeks remaining.
The Information Technology Team Manager is concerned that he has no idea what the
service provider is doing about preparing to accept the transfer of Information Technology
equipment and staff. He is uncertain about what should be happening.
Which 2 initial actions should the Team Manager take in response to this concern?

Show answerHide answer

Correct answer: D, E

 Check the Information Technology Work Package for development interfaces to see
whether the service provider Team Manager should have been liaising with the Information
Technology team during development.

Raise an issue to notify the Project Manager of this concern.

Question 69 Choose 1

Which principle is supported by the activity Evaluate the Project?

Show answerHide answer

Correct answer: C

Learn from experience

Question 70 Choose 1

It is now late October and the project is in stage 3. The label design competition has been
held and the photos of the staff have been taken. The CEO and Marketing Director still
need to choose the winning label design and the 12 photos for the calendar. However, the
Executive has learned that two competitors are issuing calendars to MNO's customers by
the middle of November. After analyzing the impact of this Issue, one of the options the
Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if
the project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the
same time was identified at the beginning of the project but the assessment of this risk
appears to have been poor?

Show answerHide answer

Correct answer: C

Lessons Report

Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt