Who is responsible for the initial creation of the Configuration Item records?
Show answerHide answer
Correct answer: D
Project Support
PRINCE2 Practitioner Exam
Free PRINCE2-Practitioner questions on Topic 9: Starting up and Initiating a Project, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Who is responsible for the initial creation of the Configuration Item records?
Correct answer: D
Project Support
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document
Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues, lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reports
to the Project Board.
This question provides a number of changes which may or may not be required to the
Extract from the Communication Management Strategy provided in the additional
information. Which statement applies to the Tools and techniques section?
Correct answer: B
Move entry 4 to Reporting because this describes a report on the performance of the
Communication procedures used.
M1ich statement is an appropriate entry for the outline Business Case heading within the
Project Brief?
Correct answer: C
The project will run for two years and the benefits will be realized over 1a years.
During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?
Correct answer: B
Project Product Description because this contains details of the expected performance
of the project's products.
Which statement is an appropriate entry for the project approach heading within the Project
Brief?
Correct answer: C
The Information Technology Division and the Facilities Division will be outsourced to a
single service provider.
Which statement is an appropriate entry for the Initiation Stage Plan?
Correct answer: B
The plan is based on the external outsourcing consultants being available at the start of
the initiation stage.
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues, lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reports
to the Project Board.
Without a Risk Register how can project risks, the progress of risk actions taken to date
and the current status of residual risks be measured?
Correct answer: A
The Daily Log was correctly used to monitor risks during the Starting up a Project
process. It will be used to capture all risks, actions, decisions, assumptions
While capturing previous lessons, the Project Manager discovered several interesting facts
about outsourcing.
Which fact is an appropriate lesson for the Outsourcing project?
Correct answer: C
Contracts with service providers should include the timescale within which readiness for
service is expected following the transfer of equipment and staff.
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues. lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reportsto the Project Board.
There is no Project Brief. How can there be a common understanding of the desired
outcomes for the prepared calendar pack?
Correct answer: C
The simple Project Initiation Documentation contains the project definition.
You've seen the free 30% (9 of 30 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2-Practitioner mock exam